Which other notices does an Ontario construction project need?

Ontario's Construction Projects regulation adds other notices. The constructor notifies the Ministry before trench work that needs no notice of project, and gives notice at least 48 hours before a suspended work platform is first used. The employer files with a Director before a tunnel or caisson. Where five or more workers work at once, a supervisor inspects weekly.

Before the work, and while it runs

Three notices go in before a kind of work starts: the trench notice where no notice of project is required, the suspended work platform notice at least 48 hours before first use, and the tunnel notice with the engineer's drawings. Three duties run for as long as the work does: the site notice, the weekly inspection where five or more workers work at once, and the emergency procedures.

DutyWindow and sectionIf missed
Notify the nearest Ministry office before work begins on a project with an enterable trench over 1.2 metres deep, where no notice of project is requirednone setreg 7an offenceLapsed compliance
Give the Ministry the approved notification form at least 48 hours before a suspended work platform system is first used at a project48 hoursreg 7.1an offenceLapsed compliance
File a notice with a Director, with engineer-sealed drawings of the support system, before beginning work on a tunnel, shaft, caisson or cofferdamnone setreg 245an offenceLapsed compliance
Post at the project the constructor's name, head office and the nearest Ministry office, and add the health and safety representative or committee members within 48 hours of their selection48 hoursreg 13(1), (2)an offenceLapsed compliance
Appoint a supervisor where five or more workers work at the same time, and have the supervisor inspect machinery, equipment and structures at least weekly7 daysreg 14(1)-(5), 15an offenceLapsed compliance
Establish written emergency procedures for the project, review them with the committee or representative, post them, and give every worker two-way communicationnone setreg 17, 18an offenceLapsed compliance

What the library notes on each duty

Quoted a whole sentence at a time from the library's note on each row.

Notify the nearest Ministry office before work begins on a project with an enterable trench over 1.2 metres deep, where no notice of project is required

reg 7 · none set · an offence

  • Binds the constructor, in person, by telephone or by fax.
  • Applies only where reg 6 does not.
  • 'Before any work at the project is begun', with no day count, so no window is recorded.

Give the Ministry the approved notification form at least 48 hours before a suspended work platform system is first used at a project

reg 7.1 · 48 hours · an offence

  • Binds the constructor: by fax, in person at the nearest Ministry office or online (reg 7.1(2)).
  • In an emergency the system may be used first after oral notice to an inspector, with the form within 24 hours of first use (reg 7.1(3), (4)).
  • A copy is kept in a conspicuous place at the project (reg 7.1(5)).

File a notice with a Director, with engineer-sealed drawings of the support system, before beginning work on a tunnel, shaft, caisson or cofferdam

reg 245 · none set · an offence

  • Binds the employer who will construct it.
  • The notice describes the work, gives profiles, sections and plans signed and sealed by the engineer who designed the support system, details all temporary and permanent ground support, names the constructor, owner, employer and supervisor in charge, locates the work, and states its start date and duration (reg 245(2)).
  • 'Before beginning work', with no day count, so no window is recorded.

Post at the project the constructor's name, head office and the nearest Ministry office, and add the health and safety representative or committee members within 48 hours of their selection

reg 13(1), (2) · 48 hours · an offence

  • Binds the constructor, in a conspicuous place, kept posted while work is done (reg 13(1)).
  • The 48 hours apply only to adding the name, trade and employer of the representative or each committee member (reg 13(2)).

Appoint a supervisor where five or more workers work at the same time, and have the supervisor inspect machinery, equipment and structures at least weekly

reg 14(1)-(5), 15 · 7 days · an offence

  • The constructor appoints a supervisor for the project (reg 14(1)), and each employer of five or more workers on the project one for its workers (reg 15).
  • The supervisor or a competent person inspects machinery and equipment, fire extinguishing equipment, magazines, electrical installations, communications, sanitation and medical facilities, structures, temporary supports and access and egress at least once a week (reg 14(3), (4)).

Establish written emergency procedures for the project, review them with the committee or representative, post them, and give every worker two-way communication

reg 17, 18 · none set · an offence

  • Binds the constructor, which must also ensure the procedures are followed (reg 17(1)).

The notice of project

A project that meets a threshold also needs a notice of project before work begins. Contravening the Act or a regulation is an offence: an individual faces a fine of up to CAD 500,000, up to 12 months' imprisonment, or both, and a corporation a fine of up to CAD 2,000,000 (OHSA s 66(1), (2)).

What this page is, and is not

It is the section text this library holds for Ontario's Construction Act, R.S.O. 1990, c. C.30 (Ontario), the Occupational Health and Safety Act, R.S.O. 1990, c. O.1 (Ontario) and Construction Projects, O. Reg. 213/91 (Ontario), with the window and the consequence. It is not legal advice, and it is not a substitute for reading the Acts, the regulations and the contract you signed.

Demiton does not yet track Ontario projects. These pages set out the duties; the product does not run these checks on an Ontario job today.

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.

Common questions

When is a trench notice needed in Ontario?

Notify the nearest Ministry office before work begins on a project with an enterable trench over 1.2 metres deep, where no notice of project is required (reg 7).

How much notice before a suspended work platform is used?

Give the Ministry the approved notification form at least 48 hours before a suspended work platform system is first used at a project (reg 7.1). In an emergency the system may be used first after oral notice to an inspector, with the form within 24 hours of first use (reg 7.1(3), (4)).

Who files the tunnel notice?

File a notice with a Director, with engineer-sealed drawings of the support system, before beginning work on a tunnel, shaft, caisson or cofferdam (reg 245).

What goes on the constructor's site notice?

Post at the project the constructor's name, head office and the nearest Ministry office, and add the health and safety representative or committee members within 48 hours of their selection (reg 13(1), (2)). The 48 hours apply only to adding the name, trade and employer of the representative or each committee member (reg 13(2)).

How often must a supervisor inspect the site?

Appoint a supervisor where five or more workers work at the same time, and have the supervisor inspect machinery, equipment and structures at least weekly (reg 14(1)-(5), 15). The supervisor or a competent person inspects machinery and equipment, fire extinguishing equipment, magazines, electrical installations, communications, sanitation and medical facilities, structures, temporary supports and access and egress at least once a week (reg 14(3), (4)).

Are written emergency procedures required?

Establish written emergency procedures for the project, review them with the committee or representative, post them, and give every worker two-way communication (reg 17, 18).