Which laws set a contractor's payment and safety duties in Ireland?
Two instruments do most of the work on an Irish construction job. The Construction Contracts Act 2013 sets when you claim, when the other party must respond and pay, and how a payment dispute goes to adjudication. The Construction Regulations 2013 set who supervises safety, who notifies the Health and Safety Authority, and who holds a Safe Pass card.
Payment: the Construction Contracts Act 2013
The contract sets the payment claim dates, or the Act's Schedule does. The payment claim notice is due within 5 days of each claim date, a contested claim gets a response within 21 days, and where the Schedule applies payment is due within 30 days. A pay when paid term is ineffective, except after the third party's insolvency event listed in s 3(6) (winding up, receivership, examinership, bankruptcy adjudication, or the equivalent under EU insolvency law).
How the Act works, or read every duty the library holds from the Construction Contracts Act 2013 (Ireland).
- Payment claimsThe payment claim notice within 5 days after the claim date, the response within 21 days, payment within 30 days, and pay when paid, under Ireland's Act.
- AdjudicationAdjudication under Ireland's Construction Contracts Act 2013: notice of intention, adjudicator within 5 days, referral within 7 days, decision within 28 days.
- Which contractsWhich contracts Ireland's Construction Contracts Act 2013 governs: the start date, the contracts left out, the services it covers, and contracting out.
Safety: the Construction Regulations 2013
The client appoints the two project supervisors: appoint in writing a competent project supervisor for the design process before design starts, and one for the construction stage before construction work starts, and get each appointee's written acceptance (reg 6(1)-(5), 7(1), 7(3), 24(2)). Required only where the work involves a particular risk (Schedule 1 lists falls from height, burial under earthfalls, work near high voltage lines, wells, underground earthworks and tunnels, explosives and others), more than one contractor is involved, or the project must be notified under reg 10. And for the workers: make sure every construction worker under your direct control holds a valid Safe Pass card, and a construction skills card for any task Schedule 5 lists (reg 4(2)-(4), 25(1); Sch 4 para 2 (S.I. No. 129 of 2019 reg 4), Sch 5).
How the Regulations work, or read every duty the library holds from the Safety, Health and Welfare at Work (Construction) Regulations 2013 (Ireland).
- PSCS and PSDPWhen the client must appoint a PSCS and a PSDP under Ireland's Construction Regulations 2013, and when a safety adviser or a safety officer is needed.
- Notifying the HSAWhich construction projects must be notified to the Health and Safety Authority, by the client and by the PSCS, the thresholds, and what goes on site display.
- Safety and health plan, safety fileWho develops the safety and health plan before construction starts, who feeds the safety file, and who keeps it after handover, under Ireland's Regulations.
- Safe PassWho needs a Safe Pass card and a construction skills card on an Irish site, how long a card lasts, and the first day confirmation the contractor gives the PSCS.
What this page is, and is not
It is the section text this library holds for Ireland's Construction Contracts Act 2013 (Ireland) and Safety, Health and Welfare at Work (Construction) Regulations 2013 (Ireland), with the window and the consequence. It is not legal advice, and it is not a substitute for reading the Act, the Regulations and the contract you signed.