Ireland / Construction Regulations 2013 / PSCS and PSDP

Who must appoint a PSCS and a PSDP, and what do they do?

The PSDP is the project supervisor for the design process and the PSCS is the project supervisor for the construction stage. Under Ireland's Construction Regulations 2013 the client appoints both, in writing, before design and before construction start, on any project with a particular risk, more than one contractor, or a notifiable size.

The appointments, and who else a site needs

The client appoints the two supervisors. The PSCS appoints a safety adviser on a large site, and every contractor appoints safety officers once enough people are under its direct control. The thresholds are in each duty below.

DutyWindow and sectionIf missed
Appoint in writing a competent project supervisor for the design process before design starts, and one for the construction stage before construction work starts, and get each appointee's written acceptancenone setreg 6(1)-(5), 7(1), 7(3), 24(2)an offenceLapsed compliance
Appoint in writing a full-time competent safety adviser for a site that normally has more than 100 people engaged in construction work at any one timenone setreg 18an offenceLapsed compliance
Appoint in writing one or more competent safety officers when more than 20 people on a site, or 30 in construction work, are under your direct controlnone setreg 26(1)-(4)an offenceLapsed compliance
Give the project supervisor information on every accident or dangerous occurrence you must notify or report, with a copy of the notificationnone setreg 24(1)(d), 17(1)(e)an offenceLapsed compliance

What the library notes on each duty

Quoted a whole sentence at a time from the library's note on each row.

Appoint in writing a competent project supervisor for the design process before design starts, and one for the construction stage before construction work starts, and get each appointee's written acceptance

reg 6(1)-(5), 7(1), 7(3), 24(2) · none set · an offence

  • Binds the client.
  • Required only where the work involves a particular risk (Schedule 1 lists falls from height, burial under earthfalls, work near high voltage lines, wells, underground earthworks and tunnels, explosives and others), more than one contractor is involved, or the project must be notified under reg 10.
  • Before the design process or construction work starts, with no day count, so no window is recorded.
  • The client may appoint itself, or one person to both roles, if competent (reg 6(2)), and must be satisfied each appointee has allocated adequate resources (reg 7).
  • A contractor that is not aware of the appointments must promptly tell the client of its duties under reg 6 (reg 24(2)).

Appoint in writing a full-time competent safety adviser for a site that normally has more than 100 people engaged in construction work at any one time

reg 18 · none set · an offence

  • Binds the project supervisor for the construction stage.
  • A standing duty triggered by headcount, with no window.

Appoint in writing one or more competent safety officers when more than 20 people on a site, or 30 in construction work, are under your direct control

reg 26(1)-(4) · none set · an offence

  • Binds every contractor that normally has that many people under its direct control at any one time.
  • One safety officer may serve a group of sites or several contractors jointly (reg 26(3)), and the site's safety adviser may also be its safety officer (reg 26(4)).

Give the project supervisor information on every accident or dangerous occurrence you must notify or report, with a copy of the notification

reg 24(1)(d), 17(1)(e) · none set · an offence

  • Binds every contractor.
  • No day count, so no window is recorded.
  • The project supervisor keeps a record of what contractors provide and must answer the Authority's request for it as soon as possible (reg 17(1)(e)).

What the PSCS does next

The PSCS notifies the HSA, develops the safety and health plan and keeps the record of each contractor's Safe Pass confirmations.

What this page is, and is not

It is the section text this library holds for Ireland's Construction Contracts Act 2013 (Ireland) and Safety, Health and Welfare at Work (Construction) Regulations 2013 (Ireland), with the window and the consequence. It is not legal advice, and it is not a substitute for reading the Act, the Regulations and the contract you signed.

Demiton does not yet track Irish projects. These pages set out the duties; the product does not run these checks on an Irish job today.

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.

Common questions

What do PSCS and PSDP stand for?

PSDP is the project supervisor for the design process. PSCS is the project supervisor for the construction stage.

Who appoints the PSCS and the PSDP?

Appoint in writing a competent project supervisor for the design process before design starts, and one for the construction stage before construction work starts, and get each appointee's written acceptance (reg 6(1)-(5), 7(1), 7(3), 24(2)). Required only where the work involves a particular risk (Schedule 1 lists falls from height, burial under earthfalls, work near high voltage lines, wells, underground earthworks and tunnels, explosives and others), more than one contractor is involved, or the project must be notified under reg 10.

Can the client be the PSCS?

The client may appoint itself, or one person to both roles, if competent (reg 6(2)), and must be satisfied each appointee has allocated adequate resources (reg 7).

When is a safety adviser needed?

Appoint in writing a full-time competent safety adviser for a site that normally has more than 100 people engaged in construction work at any one time (reg 18).

When is a safety officer needed?

Appoint in writing one or more competent safety officers when more than 20 people on a site, or 30 in construction work, are under your direct control (reg 26(1)-(4)).

What must a contractor tell the PSCS after an accident?

Give the project supervisor information on every accident or dangerous occurrence you must notify or report, with a copy of the notification (reg 24(1)(d), 17(1)(e)).