What do Ireland's Construction Regulations 2013 require on site?

The Safety, Health and Welfare at Work (Construction) Regulations 2013 set the safety roles on an Irish construction project. The client appoints a project supervisor for the design process (PSDP) and one for the construction stage (PSCS). The PSCS notifies the Health and Safety Authority, develops the safety and health plan and keeps the record of Safe Pass confirmations.

Who does what

  1. The client appoints the supervisors. Appoint in writing a competent project supervisor for the design process before design starts, and one for the construction stage before construction work starts, and get each appointee's written acceptance (reg 6(1)-(5), 7(1), 7(3), 24(2)).
  2. The PSCS notifies the HSA. Notify the Health and Safety Authority in writing, before construction work begins, with the particulars Schedule 3 lists, when the work will last more than 30 working days or exceed 500 person days, and display those particulars on site (reg 22(1), 22(2); Sch 3).
  3. The PSCS runs the plan. Develop the safety and health plan before construction work starts, keep it adjusted as the work progresses, and bring it and its rules to the attention of every contractor (reg 16; 24(1)(g)-(i)).
  4. Every contractor checks the cards. Make sure every construction worker under your direct control holds a valid Safe Pass card, and a construction skills card for any task Schedule 5 lists (reg 4(2)-(4), 25(1); Sch 4 para 2 (S.I. No. 129 of 2019 reg 4), Sch 5). Then, on each worker's first day on site, ask to see their registration card and give the project supervisor written confirmation that they hold it and the other certificates the law requires (reg 25(2), 17(5)).

Every duty the library holds from the Regulations

In the order the library holds them. Each is on the Safety, Health and Welfare at Work (Construction) Regulations 2013 (Ireland) page too, with how it was read.

DutyWindow and sectionIf missed
Appoint in writing a competent project supervisor for the design process before design starts, and one for the construction stage before construction work starts, and get each appointee's written acceptancenone setreg 6(1)-(5), 7(1), 7(3), 24(2)an offenceLapsed compliance
Notify the Health and Safety Authority promptly, in writing on its approved form, of the project supervisor appointments when the work will last more than 30 working days or exceed 500 person daysnone setreg 10an offenceLapsed compliance
Notify the Health and Safety Authority in writing, before construction work begins, with the particulars Schedule 3 lists, when the work will last more than 30 working days or exceed 500 person days, and display those particulars on sitenone setreg 22(1), 22(2); Sch 3an offenceLapsed compliance
Develop the safety and health plan before construction work starts, keep it adjusted as the work progresses, and bring it and its rules to the attention of every contractornone setreg 16; 24(1)(g)-(i)an offenceLapsed compliance
Give the project supervisor, in writing and promptly, the information needed to prepare the safety filenone setreg 21(1), 24(1)(e)an offenceLapsed compliance
Keep the safety file available for inspection by anyone who needs it for later construction work on the structure, and hand it over when the structure is soldnone setreg 8(1)-(3), 13(b)an offenceLapsed compliance
Appoint in writing a full-time competent safety adviser for a site that normally has more than 100 people engaged in construction work at any one timenone setreg 18an offenceLapsed compliance
Appoint in writing one or more competent safety officers when more than 20 people on a site, or 30 in construction work, are under your direct controlnone setreg 26(1)-(4)an offenceLapsed compliance
Make sure every construction worker under your direct control holds a valid Safe Pass card, and a construction skills card for any task Schedule 5 listsnone setreg 4(2)-(4), 25(1); Sch 4 para 2 (S.I. No. 129 of 2019 reg 4), Sch 5an offenceLapsed compliance
On each worker's first day on site, ask to see their registration card and give the project supervisor written confirmation that they hold it and the other certificates the law requiresnone setreg 25(2), 17(5)an offenceLapsed compliance
Give the project supervisor information on every accident or dangerous occurrence you must notify or report, with a copy of the notificationnone setreg 24(1)(d), 17(1)(e)an offenceLapsed compliance

In this guide

What this page is, and is not

It is the section text this library holds for Ireland's Construction Contracts Act 2013 (Ireland) and Safety, Health and Welfare at Work (Construction) Regulations 2013 (Ireland), with the window and the consequence. It is not legal advice, and it is not a substitute for reading the Act, the Regulations and the contract you signed.

Demiton does not yet track Irish projects. These pages set out the duties; the product does not run these checks on an Irish job today.

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.

Common questions

What are the Construction Regulations 2013?

The Safety, Health and Welfare at Work (Construction) Regulations 2013 set the safety roles on an Irish construction project. The client appoints a project supervisor for the design process (PSDP) and one for the construction stage (PSCS). The PSCS notifies the Health and Safety Authority, develops the safety and health plan and keeps the record of Safe Pass confirmations.

What is a PSCS?

The project supervisor for the construction stage, appointed in writing by the client before construction work starts (reg 6(1)-(5), 7(1), 7(3), 24(2)). The PSCS notifies the HSA (reg 22(1), 22(2); Sch 3), develops the safety and health plan (reg 16; 24(1)(g)-(i)) and keeps the record of each contractor's Safe Pass confirmations (reg 25(2), 17(5)).

When is a PSCS and a PSDP needed?

Appoint in writing a competent project supervisor for the design process before design starts, and one for the construction stage before construction work starts, and get each appointee's written acceptance (reg 6(1)-(5), 7(1), 7(3), 24(2)). Required only where the work involves a particular risk (Schedule 1 lists falls from height, burial under earthfalls, work near high voltage lines, wells, underground earthworks and tunnels, explosives and others), more than one contractor is involved, or the project must be notified under reg 10.

Which projects must be notified to the HSA?

Notify the Health and Safety Authority in writing, before construction work begins, with the particulars Schedule 3 lists, when the work will last more than 30 working days or exceed 500 person days, and display those particulars on site (reg 22(1), 22(2); Sch 3). 'Promptly', with no day count, so no window is recorded; 30 working days and 500 person days are the thresholds for the duty, not its window.

How long is a Safe Pass card valid?

A card is valid for 4 years from completing the programme (Sch 4 para 2, substituted by S.I. No. 129 of 2019; the Covid-19 extensions in S.I. No. 102 of 2020 and No. 528 of 2021 have all run out).