When must a construction project be notified to the HSA?

Under Ireland's Construction Regulations 2013, two notices go to the Health and Safety Authority on a larger project. The client notifies the project supervisor appointments. The PSCS notifies the project particulars before construction work begins and displays them on site. Both apply above the same duration and person day thresholds.

Two notices, two senders

The client notifies the appointments (reg 10). The PSCS notifies the project particulars before construction work begins, and displays them on site (reg 22(1), 22(2); Sch 3). Neither notice has a day count. On the client's notice, the library notes: 'Promptly', with no day count, so no window is recorded; 30 working days and 500 person days are the thresholds for the duty, not its window.

DutyWindow and sectionIf missed
Notify the Health and Safety Authority promptly, in writing on its approved form, of the project supervisor appointments when the work will last more than 30 working days or exceed 500 person daysnone setreg 10an offenceLapsed compliance
Notify the Health and Safety Authority in writing, before construction work begins, with the particulars Schedule 3 lists, when the work will last more than 30 working days or exceed 500 person days, and display those particulars on sitenone setreg 22(1), 22(2); Sch 3an offenceLapsed compliance

What the library notes on each notice

Quoted a whole sentence at a time from the library's note on each row.

Notify the Health and Safety Authority promptly, in writing on its approved form, of the project supervisor appointments when the work will last more than 30 working days or exceed 500 person days

reg 10 · none set · an offence

  • Binds the client.
  • 'Promptly', with no day count, so no window is recorded; 30 working days and 500 person days are the thresholds for the duty, not its window.
  • Sent by registered post or as the Authority directs.

Notify the Health and Safety Authority in writing, before construction work begins, with the particulars Schedule 3 lists, when the work will last more than 30 working days or exceed 500 person days, and display those particulars on site

reg 22(1), 22(2); Sch 3 · none set · an offence

  • Binds the project supervisor for the construction stage, a role a main contractor often holds.
  • Before the work begins and 'promptly', with no day count, so no window is recorded.
  • Schedule 3 particulars include the client, both project supervisors, the site address, the planned start date and duration, the maximum number of workers on site and the contractors chosen.
  • The displayed particulars must be updated as necessary (reg 22(2)).

Before the notice

The appointments the client notifies are on PSCS and PSDP.

What this page is, and is not

It is the section text this library holds for Ireland's Construction Contracts Act 2013 (Ireland) and Safety, Health and Welfare at Work (Construction) Regulations 2013 (Ireland), with the window and the consequence. It is not legal advice, and it is not a substitute for reading the Act, the Regulations and the contract you signed.

Demiton does not yet track Irish projects. These pages set out the duties; the product does not run these checks on an Irish job today.

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.

Common questions

Which construction projects must be notified to the HSA?

Notify the Health and Safety Authority promptly, in writing on its approved form, of the project supervisor appointments when the work will last more than 30 working days or exceed 500 person days (reg 10). 'Promptly', with no day count, so no window is recorded; 30 working days and 500 person days are the thresholds for the duty, not its window.

What does the PSCS notify?

Notify the Health and Safety Authority in writing, before construction work begins, with the particulars Schedule 3 lists, when the work will last more than 30 working days or exceed 500 person days, and display those particulars on site (reg 22(1), 22(2); Sch 3).

Is there a deadline for the notice?

The client notifies promptly and the PSCS before construction work begins; neither row sets a day count. On the client's notice, the library notes: 'Promptly', with no day count, so no window is recorded; 30 working days and 500 person days are the thresholds for the duty, not its window.

Which form is used?

The client's notice is on the Authority's approved form (reg 10). The library does not hold the form itself.