What does the CLOCS Standard require of contractors in England?

CLOCS Standard Version 5 is a UK standard. The library holds its duties for three parties: the client, the principal contractor and the fleet operator. Each set of duties binds only on a condition: the client has adopted CLOCS, the client's contract or a planning condition requires it, or the contract that engages the fleet operator requires it.

Demiton is not CLOCS and accredits no one. This is an independent explainer. Every duty below is read from CLOCS Standard Version 5, November 2024, read 21 October 2026.

When it binds

CLOCS is a UK standard written up here for England, and it binds differently for each party. The client's duties are binding where the client has adopted CLOCS. The principal contractor's duties are binding only where the client's contract or a planning condition requires CLOCS. The fleet operator's duties are binding only where the contract that engages the operator requires CLOCS.

So the question on an English job is whether CLOCS applies to this contract, not to the industry. The conditions above name where to look: the client's contract, the planning conditions for the project, and the contract that engages each fleet operator.

How it differs from CLOCS-A

The two schemes share a name and not a structure. CLOCS-A is a national voluntary Standard (s 1) that binds a contractor only when the client's contract requires it (s 3), or once the contractor is accredited. Version 5 reaches a principal contractor through a planning condition as well as the contract, and it sets duties on the client, which the Australian guide does not hold.

The vehicle rules differ too. Bronze, the minimum, is met by at least one standard of each either/OR pair plus every other Bronze standard. For Version 5 the library holds a fleet operator duty to run every construction logistics heavy goods vehicle to the standards described as Silver in the FORS Standard (cl 7.1(b)), and holds no vehicle equipment list. The party that runs the vehicles is called the fleet operator here and the Transport Operator in CLOCS-A.

If you work in both countries, read the CLOCS-A guide beside this one, and the matching chapters: the logistics management plan, the traffic management plan and the Bronze vehicle equipment.

What the library holds for the client

DutyBindsWindow and clauseIf missed
As client, make sure planning and design risk assessments identify and assess the risks construction logistics poses to vulnerable road usersClientnone setcl 4.1(a)a breach of contract
As client, investigate and specify, where reasonably practicable, measures that reduce the project's heavy vehicle movementsClientnone setcl 4.1(b)a breach of contract
As client, put CLOCS requirements in the procurement strategy, tender documents and contracts, and require the principal contractor to make its site and fleet operators complyClientnone setcl 4.2(a)-(d)a breach of contract
As client, make sure the project team develops, implements and monitors a Construction Logistics Plan that meets the Standard's minimum contentClientnone setcl 4.3(a)a breach of contract
As client, monitor CLOCS compliance by requiring independent site monitoring assessments, delivery performance reports, serious incident reports and action plansClient6 monthsThe independent formal site monitoring assessment is "approximately six-monthly", so the 6-month window is the Standard's approximation, not a fixed date.cl 4.4(a)a breach of contract
As client, use the contract to require that serious construction vehicle incidents are investigated, rectified within an agreed timeframe and answered with an action plan, and review the incidents notifiedClientnone setThe timeframe is agreed in the contract; the Standard sets no number.cl 4.5(a)-(b)a breach of contract

What the library holds for the principal contractor

DutyBindsWindow and clauseIf missed
Make sure risk assessments through the life of the project identify and assess the risks construction logistics poses to vulnerable road users, including high-risk roads, junctions and routesPrincipal contractornone setcl 5.1(a)a breach of contract
Develop, implement and maintain a project-specific Construction Logistics Plan that plans and manages vehicle movements into and out of the projectPrincipal contractornone setcl 5.2(a)-(b)a breach of contract
Review and update the Construction Logistics Plan before each new phase of construction startsPrincipal contractornone setcl 5.2(c)a breach of contract
Develop, implement and maintain a Construction Traffic Management Plan that includes traffic guidance schemes and vehicle movement plansPrincipal contractornone setcl 5.3(a)-(c)a breach of contract
Put CLOCS requirements in the procurement strategy, tender documents and contracts, and require every applicable site and fleet operator to comply and give evidence of compliancePrincipal contractornone setcl 5.4(a)-(e)a breach of contract
Use a delivery management system that schedules deliveries, captures vehicle and driver details, controls peak hour traffic and tells operators the routes and site rulesPrincipal contractornone setcl 5.5(a)a breach of contract
Risk-assess and select the safest vehicle routes to and from site, and make every subcontractor, fleet operator and supplier aware they must use themPrincipal contractornone setcl 5.6(a)-(d)a breach of contract
Keep the site's ground conditions suitable for the vehicles that service it, and review them regularlyPrincipal contractornone set"Regular": the Standard states no interval, so no window is recorded.cl 5.7(a)-(b)a breach of contract
Keep site access and egress clearly marked, managed and clear of obstacles, and apply traffic management principles that minimise hazardsPrincipal contractornone setcl 5.8(a)-(c)a breach of contract
Appoint competent site access traffic marshals with formal approved training that included practical experiencePrincipal contractornone setcl 5.9(b)a breach of contract
Check vehicles and drivers against the CLOCS Standard by observation and frequent formal checks on a checklist, keep the records, and risk-assess and address every non-compliance at oncePrincipal contractornone set"Frequent": the Standard states no interval, so no window is recorded.cl 5.9(c)-(d)a breach of contract
Load and unload on site on a stable, graded surface as far as practicable, and use an off-site area only with consent and a risk assessmentPrincipal contractornone setcl 5.10(a)-(b)a breach of contract
Arrange independent formal CLOCS site monitoring assessments and give the client the evidencePrincipal contractor6 monthsThe assessment is "approximately six-monthly", so the 6-month window is the Standard's approximation, not a fixed date.cl 5.11(a)a breach of contract
Report fleet and site performance to the client every quarter, including the site access gate check results, trends and remedial actionsPrincipal contractor3 monthscl 5.11(b)-(c)a breach of contract
Report serious construction vehicle incidents to the client as soon as reasonably practicable, and investigate them to a level that matches their severityPrincipal contractornone set"As soon as reasonably practicable" states no number, so no window is recorded.cl 5.11(d)a breach of contract
Obtain and monitor an action plan wherever a site monitoring assessment or a gate check finds non-compliance, and review action plans for the risk to vulnerable road usersPrincipal contractornone setcl 5.12(b)-(d)a breach of contract
Consider engaging local schools and the community on the risks of construction trafficPrincipal contractornone setcl 5.13(a)no penalty stated

What the library holds for the fleet operator

DutyBindsWindow and clauseIf missed
Belong to a recognised independent fleet accreditation scheme, or run a management system that covers management, vehicles, drivers and operations, and give the procurer evidence of itFleet operatornone setcl 7.1(a), (c)a breach of contract
Run every construction logistics heavy goods vehicle to the standards described as Silver in the FORS StandardFleet operatornone setcl 7.1(b)a breach of contract

In this guide

Three chapters take the duties on the construction logistics plan, the construction traffic management plan and the fleet operator. The Standard, clause by clause is on its own page.

What the library does not hold

It holds the 25 duties above. It holds no row for the Standard's scope or definitions, and none for the schemes that sit beside it, such as London's Direct Vision Standard. Read the Standard for those, and the contract for which parts bind you.

What this page is, and is not

It is the section text this library holds for England, from The Construction (Design and Management) Regulations 2015 (Great Britain), Housing Grants, Construction and Regeneration Act 1996, Part II (Construction Contracts), The Scheme for Construction Contracts (England and Wales) Regulations 1998, as amended for England, and Construction Logistics and Community Safety (CLOCS) Standard, Version 5, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the Regulations, the Act, the Scheme, the CLOCS Standard and the contract you signed.

These pages explain the Standard. They do not mean Demiton checks a job against it, and the duties above are the ones the library holds, not every duty the Standard sets.

Clauses read from the obligation library, release v22, last checked against the source on .

Common questions

Is the CLOCS Standard compulsory in England?

Not by itself. The principal contractor's duties are binding only where the client's contract or a planning condition requires CLOCS. The client's duties are binding where the client has adopted CLOCS. The fleet operator's duties are binding only where the contract that engages the operator requires CLOCS.

Whom does CLOCS Standard Version 5 set duties for?

The library holds 25 duties: 6 on the client, 17 on the principal contractor and 2 on the fleet operator.

Does a fleet operator need FORS Silver?

FORS Silver accreditation itself is not a CLOCS requirement; another accreditation scheme or management system may show the same standard.

How does CLOCS differ from CLOCS-A?

CLOCS-A is a national voluntary Standard (s 1) that binds a contractor only when the client's contract requires it (s 3), or once the contractor is accredited. For Version 5, the principal contractor's duties are binding only where the client's contract or a planning condition requires CLOCS, and the library also holds client duties, which the CLOCS-A guide does not.

Does Demiton accredit contractors against CLOCS?

Demiton is not CLOCS and accredits no one. This is an independent explainer.