England / CDM Regulations 2015 / Principal designer and principal contractor

Who must appoint a principal designer and a principal contractor?

Under the CDM Regulations 2015, where more than one contractor will work on a project, the client appoints a principal designer and a principal contractor in writing before the construction phase begins. The principal designer manages health and safety in the pre-construction phase. The principal contractor manages it in the construction phase, with a site induction and welfare facilities.

The appointments, and what each role carries

Required where there is more than one contractor, or it is reasonably foreseeable that more than one will work on the project at any time. The principal designer must be a designer with control over the pre-construction phase; the principal contractor must be a contractor. The principal designer runs the pre-construction phase, the principal contractor runs the construction phase, and every contractor works to their directions.

DutyWindow and sectionIf missed
Where more than one contractor will work on the project, appoint in writing a principal designer and a principal contractor, as soon as is practicable and before the construction phase beginsnone set'As soon as is practicable' and 'before the construction phase begins', with no day count, so no window is recorded.reg 5(1)-(4)an offenceLapsed compliance
As principal designer, plan, manage, monitor and coordinate health and safety in the pre-construction phase, and liaise with the principal contractor for the whole appointmentnone setA standing duty for the appointment, with no day count, so no window is recorded.reg 11(1)-(7)an offenceLapsed compliance
As principal contractor, plan, manage, monitor and coordinate health and safety in the construction phase, provide a site induction, keep unauthorised people off site and provide welfare facilitiesnone setA standing duty for the construction phase, with no day count, so no window is recorded.reg 13(1)-(5); Sch 2an offenceLapsed compliance
Accept an appointment as designer or contractor only with the skills, knowledge, experience and organisational capability the role needs, and check the same of anyone you appointnone setBefore the appointment, with no day count, so no window is recorded.reg 8(1)-(3), 15(7)an offenceLapsed compliance
As a contractor, start work only once satisfied the client knows its duties and the site is secured, follow the principal designer's and principal contractor's directions and the plan, and supervise, instruct and induct every workernone setBefore starting work, with no day count, so no window is recorded.reg 15(1)-(3), 15(8)-(11)an offenceLapsed compliance
As principal contractor, make and keep arrangements for workers to cooperate on health, safety and welfare, consult them in good time, and let them inspect and copy the health and safety information heldnone set'In good time', with no day count, so no window is recorded.reg 14an offenceLapsed compliance
As client, make suitable arrangements for managing the project, including enough time and resources, and maintain and review them throughoutnone setA standing duty with no day count, so no window is recorded.reg 4(1)-(3), 4(6), 4(8)an offenceLapsed compliance

What the library notes on each duty

Quoted a whole sentence at a time from the library's note on each row.

Where more than one contractor will work on the project, appoint in writing a principal designer and a principal contractor, as soon as is practicable and before the construction phase begins

reg 5(1)-(4) · none set · an offence

  • Binds the client.
  • Required where there is more than one contractor, or it is reasonably foreseeable that more than one will work on the project at any time.
  • The principal designer must be a designer with control over the pre-construction phase; the principal contractor must be a contractor.
  • A client that fails to appoint must carry out the principal designer's duties (regs 11, 12) or the principal contractor's (regs 12 to 14) itself (reg 5(3), (4)); for a domestic client the designer and contractor in control take the roles instead (reg 7(2)).

As principal designer, plan, manage, monitor and coordinate health and safety in the pre-construction phase, and liaise with the principal contractor for the whole appointment

reg 11(1)-(7) · none set · an offence

  • The principal designer must take account of the general principles of prevention, identify and eliminate or control foreseeable risks so far as is reasonably practicable, ensure every designer complies with reg 9, ensure everyone in the pre-construction phase cooperates, help the client provide pre-construction information, and share with the principal contractor what is relevant to the construction phase (reg 11(7)).
  • Binds a contractor that takes the role, or a client that fails to appoint one (reg 5(3)).
  • This is the CDM principal designer only; any other instrument that uses the same title was not read.

As principal contractor, plan, manage, monitor and coordinate health and safety in the construction phase, provide a site induction, keep unauthorised people off site and provide welfare facilities

reg 13(1)-(5); Sch 2 · none set · an offence

  • The principal contractor must also organise cooperation between contractors, coordinate their compliance with health and safety law, ensure employers apply the general principles of prevention and follow the construction phase plan (reg 13(3)), and liaise with the principal designer for the whole of its appointment (reg 13(5)).
  • Schedule 2 sets the minimum welfare facilities (toilets, washing, drinking water, changing rooms and lockers, rest facilities), provided throughout the construction phase (reg 13(4)(c)).
  • Binds a client that fails to appoint a principal contractor (reg 5(4)).

Accept an appointment as designer or contractor only with the skills, knowledge, experience and organisational capability the role needs, and check the same of anyone you appoint

reg 8(1)-(3), 15(7) · none set · an offence

  • Organisational capability applies where the appointee is an organisation (reg 8(1)).
  • A person who appoints a designer or contractor must take reasonable steps to satisfy itself of this (reg 8(3)), which binds a principal contractor appointing subcontractors.
  • A contractor must not employ or appoint a person to work on site unless they have, or are obtaining, the skills, knowledge, training and experience for their tasks (reg 15(7)).

As a contractor, start work only once satisfied the client knows its duties and the site is secured, follow the principal designer's and principal contractor's directions and the plan, and supervise, instruct and induct every worker

reg 15(1)-(3), 15(8)-(11) · none set · an offence

  • Binds every contractor, including subcontractors.
  • Where there is more than one contractor, each must comply with directions from the principal designer or principal contractor and with the parts of the construction phase plan relevant to its work (reg 15(3)).
  • Worker information must include a site induction where the principal contractor has not provided one, emergency procedures, and the risks from its own and other contractors' work (reg 15(9)).

As principal contractor, make and keep arrangements for workers to cooperate on health, safety and welfare, consult them in good time, and let them inspect and copy the health and safety information held

reg 14 · none set · an offence

  • Consultation is on matters connected with the project that may affect workers' health, safety or welfare, so far as their employer has not already consulted them (reg 14(b)).
  • Information that may be withheld includes anything against national security, information about an individual without their consent, commercially damaging information and information obtained for legal proceedings (reg 14(c)(i)-(v)).

As client, make suitable arrangements for managing the project, including enough time and resources, and maintain and review them throughout

reg 4(1)-(3), 4(6), 4(8) · none set · an offence

  • Arrangements are suitable if the work can be carried out, so far as is reasonably practicable, without risk to health or safety, and the Schedule 2 welfare facilities are provided.
  • The client must also take reasonable steps to ensure the principal designer and principal contractor carry out their duties (reg 4(6)).
  • Where there is more than one client, they may agree in writing which of them is treated as the client (reg 4(8)).

What the duty holders do next

The client notifies the HSE of a notifiable project, the principal contractor draws up the construction phase plan, and the principal designer prepares the health and safety file. On a project for a domestic client, the client's duties pass to the contractor or the principal designer.

What this page is, and is not

It is the section text this library holds for England, from The Construction (Design and Management) Regulations 2015 (Great Britain), Housing Grants, Construction and Regeneration Act 1996, Part II (Construction Contracts) and The Scheme for Construction Contracts (England and Wales) Regulations 1998, as amended for England, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the Regulations, the Act, the Scheme and the contract you signed.

Demiton does not yet track English projects. These pages set out the duties; the product does not run these checks on an English job today.

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.

Common questions

When must a principal designer and a principal contractor be appointed?

Where more than one contractor will work on the project, appoint in writing a principal designer and a principal contractor, as soon as is practicable and before the construction phase begins (reg 5(1)-(4)). Required where there is more than one contractor, or it is reasonably foreseeable that more than one will work on the project at any time.

Who can be the principal designer?

The principal designer must be a designer with control over the pre-construction phase; the principal contractor must be a contractor.

What if the client appoints no one?

A client that fails to appoint must carry out the principal designer's duties (regs 11, 12) or the principal contractor's (regs 12 to 14) itself (reg 5(3), (4)); for a domestic client the designer and contractor in control take the roles instead (reg 7(2)).

What does the principal designer do?

As principal designer, plan, manage, monitor and coordinate health and safety in the pre-construction phase, and liaise with the principal contractor for the whole appointment (reg 11(1)-(7)).

What does the principal contractor do?

As principal contractor, plan, manage, monitor and coordinate health and safety in the construction phase, provide a site induction, keep unauthorised people off site and provide welfare facilities (reg 13(1)-(5); Sch 2). Schedule 2 sets the minimum welfare facilities (toilets, washing, drinking water, changing rooms and lockers, rest facilities), provided throughout the construction phase (reg 13(4)(c)).

What must every contractor do?

As a contractor, start work only once satisfied the client knows its duties and the site is secured, follow the principal designer's and principal contractor's directions and the plan, and supervise, instruct and induct every worker (reg 15(1)-(3), 15(8)-(11)).

What must be checked before an appointment?

Accept an appointment as designer or contractor only with the skills, knowledge, experience and organisational capability the role needs, and check the same of anyone you appoint (reg 8(1)-(3), 15(7)).