England / CDM Regulations 2015

What do the CDM Regulations 2015 require on a construction project?

The Construction (Design and Management) Regulations 2015 set who manages health and safety on a construction project in Great Britain. Where more than one contractor will work on it, the client appoints a principal designer and a principal contractor in writing. A notifiable project is notified to the HSE, and every project needs a construction phase plan.

Who does what, in order

  1. The client appoints the duty holders. Where more than one contractor will work on the project, appoint in writing a principal designer and a principal contractor, as soon as is practicable and before the construction phase begins (reg 5(1)-(4)).
  2. The client notifies the HSE. Where the project is notifiable, give the HSE written notice with the Schedule 1 particulars as soon as is practicable before the construction phase begins (reg 6(1)-(5); Sch 1).
  3. The principal contractor writes the plan. Draw up a construction phase plan during the pre-construction phase and before setting up the construction site, and keep it reviewed and updated throughout the project (reg 4(5)(a), 12(1)-(4), 15(5), 15(6); Sch 3).
  4. The principal designer prepares the file. Prepare a health and safety file for the project during the pre-construction phase, keep it updated, and feed it with the principal contractor's relevant information (reg 4(5)(b), 12(5)-(7), 12(9)).

Applies in Great Britain only (reg 3). On a project for a domestic client, the client's duties pass to a contractor or the principal designer.

Every duty the library holds from the Regulations

In the order the library holds them. Each is on the The Construction (Design and Management) Regulations 2015 (Great Britain) page too, with how it was read.

DutyWindow and sectionIf missed
As client, make suitable arrangements for managing the project, including enough time and resources, and maintain and review them throughoutnone setA standing duty with no day count, so no window is recorded.reg 4(1)-(3), 4(6), 4(8)an offenceLapsed compliance
Provide pre-construction information as soon as is practicable to every designer and contractor appointed, or being considered for appointmentnone set'As soon as is practicable', with no day count, so no window is recorded; any information these Regulations require must be comprehensible (reg 8(6)).reg 4(4), 8(6), 11(6)an offenceLapsed compliance
Where more than one contractor will work on the project, appoint in writing a principal designer and a principal contractor, as soon as is practicable and before the construction phase beginsnone set'As soon as is practicable' and 'before the construction phase begins', with no day count, so no window is recorded.reg 5(1)-(4)an offenceLapsed compliance
Where the project is notifiable, give the HSE written notice with the Schedule 1 particulars as soon as is practicable before the construction phase beginsnone setThese are the thresholds for the duty, not its window: 'as soon as is practicable before the construction phase begins' has no day count, so no window is recorded.reg 6(1)-(5); Sch 1an offenceLapsed compliance
Display the notification clearly in the construction site office, where any worker can read it, and update it when needednone setA standing duty for as long as the site office exists, with no day count, so no window is recorded.reg 6(3)(b), 6(3)(c)an offenceLapsed compliance
Where the client is a domestic client, carry out the client's duties under regs 4(1) to (7) and 6 as the sole contractor, the principal contractor, or the principal designer by written agreementnone setreg 2(1), 7(1)-(3), 8(7)an offenceLapsed compliance
Accept an appointment as designer or contractor only with the skills, knowledge, experience and organisational capability the role needs, and check the same of anyone you appointnone setBefore the appointment, with no day count, so no window is recorded.reg 8(1)-(3), 15(7)an offenceLapsed compliance
Draw up a construction phase plan during the pre-construction phase and before setting up the construction site, and keep it reviewed and updated throughout the projectnone setBefore the site is set up, with no day count, so no window is recorded.reg 4(5)(a), 12(1)-(4), 15(5), 15(6); Sch 3an offenceLapsed compliance
Prepare a health and safety file for the project during the pre-construction phase, keep it updated, and feed it with the principal contractor's relevant informationnone setA duty during the project, with no day count, so no window is recorded.reg 4(5)(b), 12(5)-(7), 12(9)an offenceLapsed compliance
Pass the health and safety file to the client at the end of the project, or to the principal contractor if the principal designer's appointment ends firstnone set'At the end of the project', with no day count, so no window is recorded.reg 4(7), 12(8), 12(10)an offenceLapsed compliance
As principal designer, plan, manage, monitor and coordinate health and safety in the pre-construction phase, and liaise with the principal contractor for the whole appointmentnone setA standing duty for the appointment, with no day count, so no window is recorded.reg 11(1)-(7)an offenceLapsed compliance
As principal contractor, plan, manage, monitor and coordinate health and safety in the construction phase, provide a site induction, keep unauthorised people off site and provide welfare facilitiesnone setA standing duty for the construction phase, with no day count, so no window is recorded.reg 13(1)-(5); Sch 2an offenceLapsed compliance
As principal contractor, make and keep arrangements for workers to cooperate on health, safety and welfare, consult them in good time, and let them inspect and copy the health and safety information heldnone set'In good time', with no day count, so no window is recorded.reg 14an offenceLapsed compliance
As a contractor, start work only once satisfied the client knows its duties and the site is secured, follow the principal designer's and principal contractor's directions and the plan, and supervise, instruct and induct every workernone setBefore starting work, with no day count, so no window is recorded.reg 15(1)-(3), 15(8)-(11)an offenceLapsed compliance
Record in writing the arrangements for any demolition or dismantling of a structure before that work beginsnone setBefore the work begins, with no day count, so no window is recorded.reg 16(2), 20(1), 20(2)an offenceLapsed compliance
Where an inspection of a supported excavation, cofferdam or caisson finds it unsafe, tell the person it was done for before the end of the shift, and give them a written report within 24 hours24 hoursreg 22(4), 22(5), 23(2), 23(3), 24(1), 24(2), 24(4)an offenceLapsed compliance
Keep each excavation, cofferdam or caisson inspection report available for an HSE inspector on site until the construction work is complete, and for 3 months after3 monthsreg 24(3)an offenceLapsed compliance

In this guide

What this page is, and is not

It is the section text this library holds for England, from The Construction (Design and Management) Regulations 2015 (Great Britain), Housing Grants, Construction and Regeneration Act 1996, Part II (Construction Contracts) and The Scheme for Construction Contracts (England and Wales) Regulations 1998, as amended for England, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the Regulations, the Act, the Scheme and the contract you signed.

Demiton does not yet track English projects. These pages set out the duties; the product does not run these checks on an English job today.

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.

Common questions

What are the CDM Regulations 2015?

The Construction (Design and Management) Regulations 2015 set who manages health and safety on a construction project in Great Britain. Where more than one contractor will work on it, the client appoints a principal designer and a principal contractor in writing. A notifiable project is notified to the HSE, and every project needs a construction phase plan.

Where do the CDM Regulations 2015 apply?

Applies in Great Britain only (reg 3).

Who appoints the principal designer and the principal contractor?

Where more than one contractor will work on the project, appoint in writing a principal designer and a principal contractor, as soon as is practicable and before the construction phase begins (reg 5(1)-(4)). A client that fails to appoint must carry out the principal designer's duties (regs 11, 12) or the principal contractor's (regs 12 to 14) itself (reg 5(3), (4)); for a domestic client the designer and contractor in control take the roles instead (reg 7(2)).

Which projects must be notified to the HSE?

Where the project is notifiable, give the HSE written notice with the Schedule 1 particulars as soon as is practicable before the construction phase begins (reg 6(1)-(5); Sch 1). A project is notifiable if the construction work on a site is scheduled to last longer than 30 working days and have more than 20 workers working at the same time at any point, or to exceed 500 person days (reg 6(1)); a working day is any day on which construction work takes place (reg 2(1)).

Who writes the construction phase plan?

Binds the principal contractor (reg 12(1), (4)), or the only contractor, as soon as is practicable before setting up the site (reg 15(5)); the client must ensure a plan is drawn up before the construction phase begins (reg 4(5)(a)), and the principal designer must give the principal contractor what it holds that is relevant (reg 12(3)).

Who prepares the health and safety file?

Prepare a health and safety file for the project during the pre-construction phase, keep it updated, and feed it with the principal contractor's relevant information (reg 4(5)(b), 12(5)-(7), 12(9)). Binds the principal designer, who prepares and updates the file (reg 12(5), (6)), and the principal contractor, which must give the principal designer any information it holds that is relevant to the file during the project (reg 12(7)) and takes over updating the file if the principal designer's appointment ends first (reg 12(9)).

What if the client is a domestic client?

Where the client is a domestic client, carry out the client's duties under regs 4(1) to (7) and 6 as the sole contractor, the principal contractor, or the principal designer by written agreement (reg 2(1), 7(1)-(3), 8(7)). A domestic client is one for whom a project is carried out not in the course or furtherance of its business (reg 2(1)).