conditions of contract, published by ACT Government, Edition 2. Australian Capital Territory.

3 obligations, clause by clause.

3 obligations transcribed from the conditions of contract, each held with its clause, the window it sets and what missing it costs.

Where it is writtenThe obligationWindowIf missedDisease
cll 33.3, 61, 67.1 (read in ACT v1.8)Lodge the final claim within 91 days of practical completionheld in the contract notice register91 daysthe claim is barredDisputes
ACT v1.8 special conditionsReport RFIs and change events in the monthly reportheld in the change event register5 daysa breach of contractMissed claims
ACT v1.8 special conditionsReport RFIs and change events in the monthly reportheld in the rfi register5 daysa breach of contractMissed claims

What this page is, and is not.

It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.

Common questions

What does GC21 Edition 2 General Conditions of Contract (ACT v1.8) cll 33.3, 61, 67.1 (read in ACT v1.8) require?

Lodge the final claim within 91 days of practical completion. Missing it: the claim is barred. The window is 91 days. Demiton watches it against the contract notice register.

What does GC21 Edition 2 General Conditions of Contract (ACT v1.8) ACT v1.8 special conditions require?

Report RFIs and change events in the monthly report. Missing it: a breach of contract. The window is 5 days. Demiton watches it against the change event register.

What does GC21 Edition 2 General Conditions of Contract (ACT v1.8) ACT v1.8 special conditions require?

Report RFIs and change events in the monthly report. Missing it: a breach of contract. The window is 5 days. Demiton watches it against the rfi register.