conditions of contract, published by ACT Government, Edition 2. Australian Capital Territory.
3 obligations, clause by clause.
3 obligations transcribed from the conditions of contract, each held with its clause, the window it sets and what missing it costs.
| Where it is written | The obligation | Window | If missed | Disease |
|---|---|---|---|---|
| cll 33.3, 61, 67.1 (read in ACT v1.8) | Lodge the final claim within 91 days of practical completionheld in the contract notice register | 91 days | the claim is barred | Disputes |
| ACT v1.8 special conditions | Report RFIs and change events in the monthly reportheld in the change event register | 5 days | a breach of contract | Missed claims |
| ACT v1.8 special conditions | Report RFIs and change events in the monthly reportheld in the rfi register | 5 days | a breach of contract | Missed claims |
What this page is, and is not.
It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
Common questions
What does GC21 Edition 2 General Conditions of Contract (ACT v1.8) cll 33.3, 61, 67.1 (read in ACT v1.8) require?
Lodge the final claim within 91 days of practical completion. Missing it: the claim is barred. The window is 91 days. Demiton watches it against the contract notice register.
What does GC21 Edition 2 General Conditions of Contract (ACT v1.8) ACT v1.8 special conditions require?
Report RFIs and change events in the monthly report. Missing it: a breach of contract. The window is 5 days. Demiton watches it against the change event register.
What does GC21 Edition 2 General Conditions of Contract (ACT v1.8) ACT v1.8 special conditions require?
Report RFIs and change events in the monthly report. Missing it: a breach of contract. The window is 5 days. Demiton watches it against the rfi register.
Does Demiton hold every obligation in GC21 Edition 2 General Conditions of Contract (ACT v1.8)?