NSW GC21 Edition 2 General Conditions of Contract (GC21 Ed 2)
conditions of contract, published by NSW Government (Department of Customer Service), Edition 2. New South Wales.
GC21 is the general conditions TfNSW lets its construction contracts on, and the G-series specifications are called up under it. It is thorough in the way a government form is thorough, which is to say every step has a number.
11 obligations, clause by clause.
Eight obligations the form itself sets, before the specifications it calls up.
| Where it is written | The obligation | Window | If missed | Disease |
|---|---|---|---|---|
| cl 61.1 | Submit the Final Payment Claim, with every unpaid Claim, within 13 weeks after Completionheld in the contract notice register | 91 days | the claim is barred | Disputes |
| cl 22.1 | Submit the Contract Program within 14 days after the Date of Contractheld in the programme register | 14 days | a breach of contract | Missed claims |
| cl 50.1, 50.9 | Notify a delay within 7 daysheld in the contract notice register | 7 days | reduced for each day late | Missed claims |
| cl 50.3 | Claim an extension of time within 28 days of the delay startingheld in the contract notice register | 28 days | reduced for each day late | Missed claims |
| cl 22.3 | Update the programme within 1 monthsheld in the programme register | 1 month | a breach of contract | Missed claims |
| cl 37.3, 37.8 | Notify a latent condition as soon as it is foundheld in the contract notice register | 7 days | the costs cannot be recovered | Missed claims |
| cl 68.1-68.3 | Claim a variation in writing within 28 days of the directionheld in the contract notice register | 28 days | damages only | Missed claims |
| Schedule 8 | Record day works on the day they occurheld in the day works docket register | 1 day | no penalty stated | Missed claims |
| cl 49.1, 49.4 | Notify a change in Statutory Requirements that changes the work within 7 days of becoming aware of itheld in the contract notice register | 7 days | the claim is barred | Missed claims |
| cl 48.7 | Notify an unordered variation within 7 daysheld in the contract notice register | 7 days | the claim is barred | Missed claims |
| cl 11.2 | Confirm a verbal direction in writing within 3 business daysheld in the contract notice register | 3 business days | no penalty stated | Missed claims |
What this page is, and is not.
It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
Common questions
What does GC21 Ed 2 cl 61.1 require?
Submit the Final Payment Claim, with every unpaid Claim, within 13 weeks after Completion. Missing it: the claim is barred. The window is 91 days. Demiton watches it against the contract notice register.
What does GC21 Ed 2 cl 22.1 require?
Submit the Contract Program within 14 days after the Date of Contract. Missing it: a breach of contract. The window is 14 days. Demiton watches it against the programme register.
What does GC21 Ed 2 cl 50.1, 50.9 require?
Notify a delay within 7 days. Missing it: reduced for each day late. The window is 7 days. Demiton watches it against the contract notice register.
What does GC21 Ed 2 cl 50.3 require?
Claim an extension of time within 28 days of the delay starting. Missing it: reduced for each day late. The window is 28 days. Demiton watches it against the contract notice register.
What does GC21 Ed 2 cl 22.3 require?
Update the programme within 1 months. Missing it: a breach of contract. The window is 1 month. Demiton watches it against the programme register.
Does Demiton hold every obligation in NSW GC21 Edition 2 General Conditions of Contract?
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
More in New South Wales
- Aboriginal objects and places (National Parks and Wildlife Act 1974 (NSW))2 obligations
- Building and Construction Industry Long Service Payments Act 1986 (NSW)1 obligation
- Environment protection licence (Protection of the Environment Operations Act 1997 (NSW))2 obligations
- Work Health and Safety Regulation 2025 (NSW), Part 4.5 Division 1 (Licensing of high risk work)2 obligations
- Building and Construction Industry Security of Payment Act 1999 (NSW)9 obligations
- Security of Payment Regulation 2020 (NSW)1 obligation
- GC21 (Edition 2) TfNSW General Conditions of Contract (C2-GC21 Ed 2 Rev 19)2 obligations
- TfNSW G2-C2 General Requirements (TS 01566)3 obligations · The immaculate NSW bureaucracy, with a specification for everything.