When does construction work need a SWMS?

A safe work method statement (SWMS) is the document the WHS Regulation requires before high risk construction work starts. The work is then done the way it says, and stopped when it is not. On a construction project the principal contractor gets a copy, and the statement is kept until the work is complete.

Demiton watches these duties on live jobs, against the registers they already keep, and tells the person who signs off before the window shuts. Book a 30-minute call.

The section for each duty, state by state

The library holds the SWMS duties for Queensland, New South Wales, Victoria, Western Australia, South Australia, Tasmania, Australian Capital Territory and Northern Territory.

StatePrepareFollow itCopy to the principal contractorReviewKeepKeep after a notifiable incidentPrincipal contractor obtains a copy
Queenslandr 299(1)r 300(1)-(2)r 301r 302r 303(1), (3), (4)r 303(2)r 312
New South Waless 299(1)s 300(1)-(2)s 301s 302s 303(1), (3), (4)s 303(2)s 312
Victoriar 327(1)(a)r 327(1)(b), (2)not held in the libraryr 328r 329not held in the librarynot held in the library
Western Australiar 299(1)r 300(1)-(2)r 301r 302r 303(1), (3), (4)r 303(2)r 312
South Australiar 299(1)r 300(1)-(2)r 301r 302r 303(1), (3), (4)r 303(2)r 312
Tasmaniar 299(1)r 300(1)-(2)r 301r 302r 303(1), (3), (4)r 303(2)r 312
Australian Capital Territoryr 299(1)r 300(1)-(2)r 301r 302r 303(1), (3), (4)r 303(2)r 312
Northern Territoryr 299(1)r 300(1)-(2)r 301r 302r 303(1), (3), (4)r 303(2)r 312

What each duty says

Each duty in the words of the Regulation, read once, with every state that uses those words and its section.

Prepare

  • Ensure a safe work method statement is prepared for high risk construction work before the work starts.Queensland r 299(1) · New South Wales s 299(1) · Western Australia r 299(1) · South Australia r 299(1) · Tasmania r 299(1) · Australian Capital Territory r 299(1) · Northern Territory r 299(1)
  • Prepare a safe work method statement before starting high risk construction work that poses a risk to anyone's health or safety.Victoria r 327(1)(a)

Follow it

  • Put arrangements in place so high risk construction work is done in accordance with its safe work method statement, and stop work that is not.Queensland r 300(1)-(2) · New South Wales s 300(1)-(2) · Western Australia r 300(1)-(2) · South Australia r 300(1)-(2) · Tasmania r 300(1)-(2) · Australian Capital Territory r 300(1)-(2) · Northern Territory r 300(1)-(2)
  • Perform high risk construction work in accordance with its safe work method statement, and stop work that is not.Victoria r 327(1)(b), (2)

Copy to the principal contractor

  • Give the principal contractor a copy of the safe work method statement before high risk construction work on a construction project starts.Queensland r 301 · New South Wales s 301 · Western Australia r 301 · South Australia r 301 · Tasmania r 301 · Australian Capital Territory r 301 · Northern Territory r 301

Not held in the library for Victoria.

Review

  • Review the safe work method statement, and revise it as necessary, when the relevant control measures are revised.Queensland r 302 · New South Wales s 302 · Western Australia r 302 · South Australia r 302 · Tasmania r 302 · Australian Capital Territory r 302 · Northern Territory r 302
  • Review the safe work method statement, and revise it as necessary, whenever the work changes or its controls are not controlling the risks.Victoria r 328

Keep

  • Keep a copy of the safe work method statement until the high risk construction work it covers is complete.Queensland r 303(1), (3), (4) · New South Wales s 303(1), (3), (4) · Western Australia r 303(1), (3), (4) · South Australia r 303(1), (3), (4) · Tasmania r 303(1), (3), (4) · Australian Capital Territory r 303(1), (3), (4) · Northern Territory r 303(1), (3), (4)
  • Keep a copy of the safe work method statement for the duration of the high risk construction work.Victoria r 329

Keep after a notifiable incident

  • Keep the safe work method statement for at least 2 years after a notifiable incident in connection with the work it covers.Queensland r 303(2) · New South Wales s 303(2) · Western Australia r 303(2) · South Australia r 303(2) · Tasmania r 303(2) · Australian Capital Territory r 303(2) · Northern Territory r 303(2)

Not held in the library for Victoria.

Principal contractor obtains a copy

  • As principal contractor, take all reasonable steps to obtain a copy of the safe work method statement before high risk construction work on the project starts.Queensland r 312 · New South Wales s 312 · Western Australia r 312 · South Australia r 312 · Tasmania r 312 · Australian Capital Territory r 312 · Northern Territory r 312

Not held in the library for Victoria.

What counts as high risk construction work: 18 kinds, 19 in the ACT and Victoria

The SWMS duty starts with the list of high risk construction work. As the library records it for each state:

  • QueenslandHigh risk construction work is the 18 kinds of construction work r 291 lists, among them a risk of a person falling more than 2m, a shaft or trench deeper than 1.5m, a tunnel, work on or next to a road or railway in use by traffic, and an area where powered mobile plant moves.
  • New South Wales, Western Australia, South Australia and TasmaniaHigh risk construction work is the 18 kinds of construction work provision 291 lists, among them a risk of a person falling more than 2m, a shaft or trench deeper than 1.5m, a tunnel, work on or next to a road or railway in use by traffic, and an area where powered mobile plant moves.
  • VictoriaHigh risk construction work is the 19 kinds r 322 lists, among them a risk of a person falling more than 2 metres, any demolition, a trench or shaft deeper than 1.5 metres, a tunnel, work on or adjacent to roadways or railways used by traffic, and a workplace where powered mobile plant moves.
  • Australian Capital TerritoryHigh risk construction work is the 19 kinds of construction work r 291 lists: the model's 18 (among them a risk of a person falling more than 2m, a shaft or trench deeper than 1.5m, a tunnel, work on or next to a road or railway, including light rail, in use by traffic, and an area where powered mobile plant moves) plus processing crystalline silica material with a power tool or another mechanical method (r 291(1)(s)).
  • Northern TerritoryHigh risk construction work is the 19 kinds of construction work r 291 lists, among them a risk of a person falling more than 2m on work that is not residential construction work, a risk of a person falling more than 3m on residential construction work, a shaft or trench deeper than 1.5m, a tunnel, work on or next to a road or railway in use by traffic, and an area where powered mobile plant moves.

The worker's licence for high risk work is a separate duty, on high risk work licences.

Where the states differ

  • QueenslandQueensland adds r 299(4): where the work risks a fall of more than 2m and the only controls are administrative controls or personal protective equipment, the statement must describe every control measure considered.
  • New South WalesBinds the principal contractor for a construction project (provision 292 - construction work costing $250,000 or more).
  • South AustraliaBinds the principal contractor for a construction project, which r 292 defines as construction work costing $450,000 or more (the model sets $250,000).
  • VictoriaVictoria is not harmonised: this binds an employer or self-employed person, and only where the work poses a risk to a person's health or safety.
  • VictoriaVictoria has no counterpart to the model's 2 years after a notifiable incident, and no duty on the principal contractor to obtain or receive the statement: the principal contractor's duties are the health and safety co-ordination plan (rr 335 to 337), not recorded here.

For as long as it must be kept, a copy must be readily accessible to every worker engaged to do the work (provision 303(3)) and available for inspection under the Act (303(4)).

A SWMS template, built from the Regulation

A SWMS is written for the work in front of you, and the library notes where its contents are set: Provision 299(2) and (3) set what the statement must contain; a statement another person already prepared satisfies the duty. The SWMS template builder assembles that for your state and job type: the high risk construction work the row names, where the contents are set, and the duties around the statement, each with its section, with the controls and the site details left blank. It is a scaffold, not a completed SWMS. How long each record is kept, after an incident too, is on records.

What this page is, and is not

It is the section text this library holds for each state's WHS law, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the Act, the Regulation and the contract you signed.

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.

Clauses read from the obligation library, release v22, last checked against the source on .

Common questions

What is a SWMS?

A safe work method statement (SWMS) is the document the WHS Regulation requires before high risk construction work starts. The work is then done the way it says, and stopped when it is not. On a construction project the principal contractor gets a copy, and the statement is kept until the work is complete.

When is a SWMS required?

Queensland (r 299(1)), New South Wales (s 299(1)), Western Australia (r 299(1)), South Australia (r 299(1)), Tasmania (r 299(1)), Australian Capital Territory (r 299(1)) and Northern Territory (r 299(1)): Ensure a safe work method statement is prepared for high risk construction work before the work starts. Victoria (r 327(1)(a)): Prepare a safe work method statement before starting high risk construction work that poses a risk to anyone's health or safety.

Who keeps the SWMS, and for how long?

Queensland (r 303(1), (3), (4)), New South Wales (s 303(1), (3), (4)), Western Australia (r 303(1), (3), (4)), South Australia (r 303(1), (3), (4)), Tasmania (r 303(1), (3), (4)), Australian Capital Territory (r 303(1), (3), (4)) and Northern Territory (r 303(1), (3), (4)): Keep a copy of the safe work method statement until the high risk construction work it covers is complete. Victoria (r 329): Keep a copy of the safe work method statement for the duration of the high risk construction work. Queensland (r 303(2)), New South Wales (s 303(2)), Western Australia (r 303(2)), South Australia (r 303(2)), Tasmania (r 303(2)), Australian Capital Territory (r 303(2)) and Northern Territory (r 303(2)): Keep the safe work method statement for at least 2 years after a notifiable incident in connection with the work it covers. Not held in the library for Victoria.

Does the principal contractor need a copy?

Queensland (r 301), New South Wales (s 301), Western Australia (r 301), South Australia (r 301), Tasmania (r 301), Australian Capital Territory (r 301) and Northern Territory (r 301): Give the principal contractor a copy of the safe work method statement before high risk construction work on a construction project starts. Not held in the library for Victoria. Queensland (r 312), New South Wales (s 312), Western Australia (r 312), South Australia (r 312), Tasmania (r 312), Australian Capital Territory (r 312) and Northern Territory (r 312): As principal contractor, take all reasonable steps to obtain a copy of the safe work method statement before high risk construction work on the project starts. Not held in the library for Victoria. Queensland, New South Wales and Tasmania: Binds the principal contractor for a construction project (provision 292 - construction work costing $250,000 or more). Western Australia: Binds the principal contractor for a construction project, which r 292 defines by headcount, not cost: a project where 5 or more persons are, or are likely to be, working at the same time at a construction site (the model sets $250,000). South Australia: Binds the principal contractor for a construction project, which r 292 defines as construction work costing $450,000 or more (the model sets $250,000). Australian Capital Territory: Binds the principal contractor for a construction project, which r 292 defines as construction work costing $250,000 or more, or any construction work that demolishes or refurbishes a structure containing loose-fill asbestos insulation, whatever it costs. Northern Territory: Binds the principal contractor for a construction project, which r 292 defines as construction work costing $1,000,000 or more from 28 May 2026 (the model sets $250,000).

Is the SWMS duty the same in Victoria?

Victoria is not harmonised: this binds an employer or self-employed person, and only where the work poses a risk to a person's health or safety. Victoria has no counterpart to the model's 2 years after a notifiable incident, and no duty on the principal contractor to obtain or receive the statement: the principal contractor's duties are the health and safety co-ordination plan (rr 335 to 337), not recorded here.

Is there a SWMS template?

The SWMS template builder assembles a scaffold for your state and job type from the library's rows: the high risk construction work, where the contents are set, and the duties around the statement, each with its section. The controls and the site details stay blank. A SWMS is written for the work in front of you, and a scaffold is not a completed statement.