Building Industry Fairness (Security of Payment) Act 2017 (Qld) (BIF Act 2017)
Act, published by Queensland Parliament, reprint current from 28 Apr 2026. Queensland.
9 obligations, clause by clause.
9 obligations transcribed from the Act, each held with its clause, the window it sets and what missing it costs.
| Where it is written | The obligation | Window | If missed | Disease |
|---|---|---|---|---|
| ss 35, 40A, 40B | Notify the retention trust account within 5 business daysheld in the contract notice register | 5 business days | an offence | Lapsed compliance |
| s 79(2)(b) | Apply for adjudication within 30 business days if a claim is disputedheld in the contract notice register | 30 business days | no penalty stated | Disputes |
| ss 82-83 | Respond to an adjudication application within 10 business daysheld in the contract notice register | 10 business days | no penalty stated | Disputes |
| ss 67, 75(4) | Make a progress claim on the cadence the contract allowsheld in the progress claim register | 1 month | no penalty stated | Disputes |
| s 68(1) | Make every claim a valid payment claim: identify the work and state the amountheld in the progress claim register | none set | the claim is barred | Disputes |
| s 73(1)(b) | Be paid within 10 business days of a payment schedule (or of the claim if none is given)held in the progress claim register | 10 business days | no penalty stated | Disputes |
| s 99 | Give notice of intention to apply for adjudication within 30 business daysheld in the contract notice register | 30 business days | no penalty stated | Disputes |
| s 76(1), s 77 | Receive a payment schedule within 15 business days of each claim, or the full amount becomes payableheld in the payment schedule register | 15 business days | you are liable for the full amount | Disputes |
| s 75(6), (8) | Attach a supporting statement that subcontractors have been paidheld in the progress claim register | none set | an offence | Lapsed compliance |
Work out a payment schedule or adjudication date under this Act with the Security of Payment deadline calculator.
How the Act works, in every state: What is the Security of Payment Act?, Payment claims, Payment schedules, Adjudication, Retention, Supporting statements, Missed deadlines, By state.
Security of Payment in the other states: Security of Payment Act NSW, Security of Payment Act Vic, Security of Payment Act WA, Security of Payment Act SA, Security of Payment Act Tas, Security of Payment Act ACT, Security of Payment Act NT.
What this page is, and is not.
It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
Common questions
What does BIF Act 2017 ss 35, 40A, 40B require?
Notify the retention trust account within 5 business days. Missing it: an offence. The window is 5 business days. Demiton watches it against the contract notice register.
What does BIF Act 2017 s 79(2)(b) require?
Apply for adjudication within 30 business days if a claim is disputed. Missing it: no penalty stated. The window is 30 business days. Demiton watches it against the contract notice register.
What does BIF Act 2017 ss 82-83 require?
Respond to an adjudication application within 10 business days. Missing it: no penalty stated. The window is 10 business days. Demiton watches it against the contract notice register.
What does BIF Act 2017 ss 67, 75(4) require?
Make a progress claim on the cadence the contract allows. Missing it: no penalty stated. The window is 1 month. Demiton watches it against the progress claim register.
What does BIF Act 2017 s 68(1) require?
Make every claim a valid payment claim: identify the work and state the amount. Missing it: the claim is barred. The clause sets no day count. Demiton watches it against the progress claim register.
Does Demiton hold every obligation in Building Industry Fairness (Security of Payment) Act 2017 (Qld)?
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
More in Queensland
- Aboriginal cultural heritage (Aboriginal Cultural Heritage Act 2003 (Qld))1 obligation
- Building and Construction Industry (Portable Long Service Leave) Act 1991 (Qld)1 obligation
- Environmental authority (Environmental Protection Act 1994 (Qld))2 obligations
- Environmental Protection Act 1994 (Qld)2 obligations
- Work Health and Safety Regulation 2011 (Qld), Part 4.5 Division 1 (Licensing of high risk work)2 obligations
- Queensland Building and Construction Commission Act 19914 obligations
- TMR Contract Administration Procedure CAP010M1 obligation · The procedure that says how the procedure is done.
- TMR MRTS04 General Earthworks1 obligation · The one that decides whether the dirt is good enough.