4 obligations, clause by clause.

4 obligations transcribed from the Act, each held with its clause, the window it sets and what missing it costs.

Where it is writtenThe obligationWindowIf missedDisease
s 67NCNotify the end of the defects liability period within 10 business daysheld in the contract_notice register10 business daysbreachDisputes
ss 67K-67NHold no more retention than the statutory capheld in the retention_position registernone setbarredDisputes
ss 67NA, 67NBRecover retention within 12 months of the defects period endingheld in the retention_position register12 monthsoffenceDisputes
s 67J(2)Challenge a set-off from retention within 28 daysheld in the contract_notice register28 daysbarredMissed claims

What this page is, and is not.

It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.

Common questions

What does QBCC Act 1991 s 67NC require?

Notify the end of the defects liability period within 10 business days. Missing it: breach. The window is 10 business days. Demiton watches it against the contract_notice register.

What does QBCC Act 1991 ss 67K-67N require?

Hold no more retention than the statutory cap. Missing it: barred. The clause sets no day count. Demiton watches it against the retention_position register.

What does QBCC Act 1991 ss 67NA, 67NB require?

Recover retention within 12 months of the defects period ending. Missing it: offence. The window is 12 months. Demiton watches it against the retention_position register.

What does QBCC Act 1991 s 67J(2) require?

Challenge a set-off from retention within 28 days. Missing it: barred. The window is 28 days. Demiton watches it against the contract_notice register.