Queensland Building and Construction Commission Act 1991 (QBCC Act 1991)
Act, published by Queensland Parliament. Queensland.
4 obligations, clause by clause.
4 obligations transcribed from the Act, each held with its clause, the window it sets and what missing it costs.
| Where it is written | The obligation | Window | If missed | Disease |
|---|---|---|---|---|
| s 67NC | Notify the end of the defects liability period within 10 business daysheld in the contract notice register | 10 business days | a breach of contract | Disputes |
| ss 67K-67N | Hold no more retention than the statutory capheld in the retention position register | none set | the claim is barred | Disputes |
| ss 67NA, 67NB | Recover retention within 12 months of the defects period endingheld in the retention position register | 12 months | an offence | Disputes |
| s 67J(2) | Challenge a set-off from retention within 28 daysheld in the contract notice register | 28 days | the claim is barred | Missed claims |
What this page is, and is not.
It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
Common questions
What does QBCC Act 1991 s 67NC require?
Notify the end of the defects liability period within 10 business days. Missing it: a breach of contract. The window is 10 business days. Demiton watches it against the contract notice register.
What does QBCC Act 1991 ss 67K-67N require?
Hold no more retention than the statutory cap. Missing it: the claim is barred. The clause sets no day count. Demiton watches it against the retention position register.
What does QBCC Act 1991 ss 67NA, 67NB require?
Recover retention within 12 months of the defects period ending. Missing it: an offence. The window is 12 months. Demiton watches it against the retention position register.
What does QBCC Act 1991 s 67J(2) require?
Challenge a set-off from retention within 28 days. Missing it: the claim is barred. The window is 28 days. Demiton watches it against the contract notice register.
Does Demiton hold every obligation in Queensland Building and Construction Commission Act 1991?
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
More in Queensland
- Aboriginal cultural heritage (Aboriginal Cultural Heritage Act 2003 (Qld))1 obligation
- Building and Construction Industry (Portable Long Service Leave) Act 1991 (Qld)1 obligation
- Building Industry Fairness (Security of Payment) Act 2017 (Qld)9 obligations
- Environmental authority (Environmental Protection Act 1994 (Qld))2 obligations
- Environmental Protection Act 1994 (Qld)2 obligations
- Work Health and Safety Regulation 2011 (Qld), Part 4.5 Division 1 (Licensing of high risk work)2 obligations
- TMR Contract Administration Procedure CAP010M1 obligation · The procedure that says how the procedure is done.
- TMR MRTS04 General Earthworks1 obligation · The one that decides whether the dirt is good enough.