TMR Contract Administration Procedure CAP010M (CAP010M)

specification, published by Queensland Department of Transport and Main Roads. Queensland.

CAP010M is not the contract. It is the manual for administering it, which is why the final claim's deadline lives here and not in the conditions of contract.

The detail it turns onclauses 5, 37 and 42final claimsecurity and retention release

1 obligation, clause by clause.

One obligation: the final claim, due within twenty business days of practical completion. The procedure cites the conditions of contract clauses it administers.

Where it is writtenThe obligationWindowIf missedDisease
cll 5, 37, 42 (via CAP010M)Lodge the final claim within 20 business days of practical completionheld in the contract_notice register20 business daysbarredDisputes

What this page is, and is not.

It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.

Common questions

What does CAP010M cll 5, 37, 42 (via CAP010M) require?

Lodge the final claim within 20 business days of practical completion. Missing it: barred. The window is 20 business days. Demiton watches it against the contract_notice register.