Queensland TMR Transport Infrastructure Contract (TIC)
conditions of contract, published by Queensland Department of Transport and Main Roads, C7830, May 2026. Queensland.
She runs Queensland's roads by a book so thick it has its own index. You respect her enormously, and you confirm every handshake in writing, because a verbal direction has ten business days to live and then it is dead.
8 obligations, clause by clause.
The eight obligations the TIC itself sets. The specifications it calls up (MRTS04, MRTS50) and the administration procedure (CAP010M) are held separately.
| Where it is written | The obligation | Window | If missed | Disease |
|---|---|---|---|---|
| cl 33.2.1, 33.2.2 | Submit the daily report within 1 business daysheld in the site diary register | 1 business day | a breach of contract | Missed claims |
| cl 35.5(c), (h), (l) | Claim an extension of time within 20 business days of the delay startingheld in the contract notice register | 20 business days | the claim is barred | Missed claims |
| cl 35.5(a) | Notify a possible delay within 10 business daysheld in the contract notice register | 10 business days | the claim is barred | Missed claims |
| cl 33.4.9 | Update the programme within 1 monthsheld in the programme register | 1 month | a breach of contract | Missed claims |
| cl 12.2, 12.4 | Notify a latent condition as soon as it is foundheld in the contract notice register | 1 business day | the costs cannot be recovered | Missed claims |
| cl 41(a) | Record day works on the day they occurheld in the day works docket register | 1 day | no penalty stated | Missed claims |
| cl 33.1(f), (g) | Confirm a verbal direction in writing within 10 business daysheld in the contract notice register | 10 business days | the claim is barred | Missed claims |
| cl 46.1 | Give the prescribed notice for a variation claim within 20 business daysheld in the contract notice register | 20 business days | the costs cannot be recovered | Missed claims |
What this page is, and is not.
It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
Common questions
What does TIC cl 33.2.1, 33.2.2 require?
Submit the daily report within 1 business days. Missing it: a breach of contract. The window is 1 business day. Demiton watches it against the site diary register.
What does TIC cl 35.5(c), (h), (l) require?
Claim an extension of time within 20 business days of the delay starting. Missing it: the claim is barred. The window is 20 business days. Demiton watches it against the contract notice register.
What does TIC cl 35.5(a) require?
Notify a possible delay within 10 business days. Missing it: the claim is barred. The window is 10 business days. Demiton watches it against the contract notice register.
What does TIC cl 33.4.9 require?
Update the programme within 1 months. Missing it: a breach of contract. The window is 1 month. Demiton watches it against the programme register.
What does TIC cl 12.2, 12.4 require?
Notify a latent condition as soon as it is found. Missing it: the costs cannot be recovered. The window is 1 business day. Demiton watches it against the contract notice register.
Does Demiton hold every obligation in Queensland TMR Transport Infrastructure Contract?
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
More in Queensland
- Aboriginal cultural heritage (Aboriginal Cultural Heritage Act 2003 (Qld))1 obligation
- Building and Construction Industry (Portable Long Service Leave) Act 1991 (Qld)1 obligation
- Building Industry Fairness (Security of Payment) Act 2017 (Qld)9 obligations
- Environmental authority (Environmental Protection Act 1994 (Qld))2 obligations
- Environmental Protection Act 1994 (Qld)2 obligations
- Work Health and Safety Regulation 2011 (Qld), Part 4.5 Division 1 (Licensing of high risk work)2 obligations
- Queensland Building and Construction Commission Act 19914 obligations
- TMR Contract Administration Procedure CAP010M1 obligation · The procedure that says how the procedure is done.