TMR MRTS50 Specific Quality System Requirements (MRTS50)
specification, published by Queensland Department of Transport and Main Roads, March 2025. Queensland.
MRTS50 is where the quality system lives, and where a certificate quietly waits on a drawing. It is also the document that decides whether a nonconformance is a conversation or a breach.
3 obligations, clause by clause.
Three obligations: the as-constructed handover, the one-working-day nonconformance notice, and the twelve-month record retention after the Final Certificate.
| Where it is written | The obligation | Window | If missed | Disease |
|---|---|---|---|---|
| cl 12.1 | Hand over the As Constructed drawings before the Certificate of Practical Completion can issueheld in the drawing_register register | none set | barred | Rework |
| cl 11.2 | Keep the contract's records for at least 12 months after the Final Certificateheld in the drawing_register register | 12 months | breach | Disputes |
| cl 10.2 | Notify a nonconformance within 1 working day of detecting it, where it meets a notifiable triggerheld in the safety_ncr register | 1 working day | breach | Rework |
What this page is, and is not.
It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
Common questions
What does MRTS50 cl 12.1 require?
Hand over the As Constructed drawings before the Certificate of Practical Completion can issue. Missing it: barred. The clause sets no day count. Demiton watches it against the drawing_register register.
What does MRTS50 cl 11.2 require?
Keep the contract's records for at least 12 months after the Final Certificate. Missing it: breach. The window is 12 months. Demiton watches it against the drawing_register register.
What does MRTS50 cl 10.2 require?
Notify a nonconformance within 1 working day of detecting it, where it meets a notifiable trigger. Missing it: breach. The window is 1 working day. Demiton watches it against the safety_ncr register.
Does Demiton hold every obligation in TMR MRTS50 Specific Quality System Requirements?
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
More in Queensland
- Building Industry Fairness (Security of Payment) Act 2017 (Qld)9 obligations
- Environmental Protection Act 1994 (Qld)2 obligations
- Queensland Building and Construction Commission Act 19914 obligations
- TMR Contract Administration Procedure CAP010M1 obligation · The procedure that says how the procedure is done.
- TMR MRTS04 General Earthworks1 obligation · The one that decides whether the dirt is good enough.
- Queensland TMR Transport Infrastructure Contract8 obligations · The thorough Queensland matriarch of the roads.
- Work Health and Safety Act 2011 (Qld)3 obligations
- Work Health and Safety Regulation 2011 (Qld)1 obligation