Construction Contracts Act 2002 (NZ)
Act, published by New Zealand Parliament, version as at 5 October 2023. New Zealand.
20 obligations, clause by clause.
20 obligations transcribed from the Act, each held with its clause, the window it sets and what missing it costs.
| Where it is written | The obligation | Window | If missed | Disease |
|---|---|---|---|---|
| s 18D, 18E, 18FB, 18DA | Hold retention money in a complying trust accountheld in the retention position register | none set | an offence | Lapsed compliance |
| s 18C(3)(c), 18DA(3) | Notify use of retention for a defect within 10 working daysheld in the contract notice register | 10 working days | the claim is barred | Disputes |
| s 18E(4)-(6), 18EA | Maintain a ledger of the retention trust accountheld in the retention position register | none set | no penalty stated | Disputes |
| s 18FC | Give the retention trust account records to whoever the Act namesheld in the retention position register | none set | an offence | Lapsed compliance |
| Sch 1 cl 1 | Determine which retention regime applies to the contract | none set | no penalty stated | Disputes |
| s 18I, 18G | Release retention on the terms the Act setsheld in the retention position register | none set | no penalty stated | Disputes |
| s 18FD | Report the retention money held every 3 monthsheld in the retention position register | 3 months | an offence | Lapsed compliance |
| s 18B(2)-(6), 18C | Keep the retention trust account in the status the Act requiresheld in the retention position register | none set | no penalty stated | Disputes |
| s 36(1), 37(1), 37A, 46(1)(b) | Respond to an adjudication claim within 5 working daysheld in the contract notice register | 5 working days | the claim is barred | Disputes |
| s 28; Regs r 5 | Give the adjudication notice the Act requiresheld in the contract notice register | none set | no penalty stated | Disputes |
| s 33(2), 35(1) | Agree on an adjudicator within 5 working days of the adjudication noticeheld in the contract notice register | 5 working days | no penalty stated | Disputes |
| s 20(1), 17(2) | Make a progress claim on the cadence the contract allowsheld in the progress claim register | 1 month | no penalty stated | Disputes |
| s 20(2) | Make every claim a valid payment claim: identify the work and state the amountheld in the progress claim register | none set | no penalty stated | Disputes |
| s 20(3)-(4); Regs r 4, Sch 1 Form 1 | Attach the prescribed Form 1 notice to every payment claimheld in the progress claim register | none set | a breach of contract | Disputes |
| s 46(2) | Issue the adjudicator's determination within 20 working daysheld in the contract notice register | 20 working days | a breach of contract | Disputes |
| s 18 | Be paid within 20 working days where the contract is silentheld in the progress claim register | 20 working days | you are liable for the full amount | Disputes |
| s 23, 24 | Recover the amount owed if payment is not made by the due dateheld in the progress claim register | none set | you are liable for the full amount | Disputes |
| s 21 | Make a payment schedule that identifies the claim and the scheduled amountheld in the payment schedule register | none set | the claim is barred | Disputes |
| s 22 | Receive a payment schedule within 20 working days of each claim, or the full amount becomes payableheld in the payment schedule register | 20 working days | you are liable for the full amount | Disputes |
| s 24A | Give 5 working days notice before suspending work for non-paymentheld in the contract notice register | 5 working days | no penalty stated | Disputes |
What this page is, and is not.
It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
Common questions
What does Construction Contracts Act 2002 (NZ) s 18D, 18E, 18FB, 18DA require?
Hold retention money in a complying trust account. Missing it: an offence. The clause sets no day count. Demiton watches it against the retention position register.
What does Construction Contracts Act 2002 (NZ) s 18C(3)(c), 18DA(3) require?
Notify use of retention for a defect within 10 working days. Missing it: the claim is barred. The window is 10 working days. Demiton watches it against the contract notice register.
What does Construction Contracts Act 2002 (NZ) s 18E(4)-(6), 18EA require?
Maintain a ledger of the retention trust account. Missing it: no penalty stated. The clause sets no day count. Demiton watches it against the retention position register.
What does Construction Contracts Act 2002 (NZ) s 18FC require?
Give the retention trust account records to whoever the Act names. Missing it: an offence. The clause sets no day count. Demiton watches it against the retention position register.
What does Construction Contracts Act 2002 (NZ) Sch 1 cl 1 require?
Determine which retention regime applies to the contract. Missing it: no penalty stated. The clause sets no day count.
Does Demiton hold every obligation in Construction Contracts Act 2002 (NZ)?
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
More in New Zealand
- Auckland Transport NZS 3910:2013 Special Conditions1 obligation
- Job budget tolerance (the contractor's own commitment)1 obligation
- Health and Safety at Work Act 20154 obligations
- NZS 3910:2013 Conditions of Contract (2013/DZ public-comment redline)17 obligations
- NZS 3910:2023 Conditions of Contract (secondary summaries; DZ draft)6 obligations