NZS 3910:2023 Conditions of Contract (secondary summaries; DZ draft)
conditions of contract, published by Standards New Zealand, 2023 ed.; published text not read. New Zealand.
6 obligations, clause by clause.
6 obligations transcribed from the conditions of contract, each held with its clause, the window it sets and what missing it costs.
| Where it is written | The obligation | Window | If missed | Disease |
|---|---|---|---|---|
| cl 9.11secondary | Submit the final account within 3 months of practical completionheld in the progress claim register | 3 months | the claim is barred | Disputes |
| DZ cl 6.10 | Give an early warning of an event likely to affect time or costheld in the contract notice register | none set | no penalty stated | Missed claims |
| cl 10.3.2 (2023); DZ 10.3.6(c)secondary | Give notice of an extension of time claim within 20 working daysheld in the contract notice register | 20 working days | no penalty stated | Missed claims |
| cl 9.2.2secondary | Notify a variation claim within 20 working days of the instructionheld in the contract notice register | 20 working days | no penalty stated | Missed claims |
| cl 9.2.3secondary | Notify any other matter affecting time or cost within 20 working daysheld in the contract notice register | 20 working days | no penalty stated | Missed claims |
| cl 9.2.5secondary | Respond to a variation notice within 20 working daysheld in the contract notice register | 20 working days | no penalty stated | Missed claims |
What this page is, and is not.
It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
Common questions
What does NZS 3910:2023 Conditions of Contract (secondary summaries; DZ draft) cl 9.11 require?
Submit the final account within 3 months of practical completion. Missing it: the claim is barred. The window is 3 months. Demiton watches it against the progress claim register.
What does NZS 3910:2023 Conditions of Contract (secondary summaries; DZ draft) DZ cl 6.10 require?
Give an early warning of an event likely to affect time or cost. Missing it: no penalty stated. The clause sets no day count. Demiton watches it against the contract notice register.
What does NZS 3910:2023 Conditions of Contract (secondary summaries; DZ draft) cl 10.3.2 (2023); DZ 10.3.6(c) require?
Give notice of an extension of time claim within 20 working days. Missing it: no penalty stated. The window is 20 working days. Demiton watches it against the contract notice register.
What does NZS 3910:2023 Conditions of Contract (secondary summaries; DZ draft) cl 9.2.2 require?
Notify a variation claim within 20 working days of the instruction. Missing it: no penalty stated. The window is 20 working days. Demiton watches it against the contract notice register.
What does NZS 3910:2023 Conditions of Contract (secondary summaries; DZ draft) cl 9.2.3 require?
Notify any other matter affecting time or cost within 20 working days. Missing it: no penalty stated. The window is 20 working days. Demiton watches it against the contract notice register.
Does Demiton hold every obligation in NZS 3910:2023 Conditions of Contract (secondary summaries; DZ draft)?
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
More in New Zealand
- Auckland Transport NZS 3910:2013 Special Conditions1 obligation
- Construction Contracts Act 2002 (NZ)20 obligations
- Job budget tolerance (the contractor's own commitment)1 obligation
- Health and Safety at Work Act 20154 obligations
- NZS 3910:2013 Conditions of Contract (2013/DZ public-comment redline)17 obligations