NZS 3910:2013 Conditions of Contract (2013/DZ public-comment redline)
conditions of contract, published by Standards New Zealand, 2013 ed.; published NZS 3910:2023 text not read. New Zealand.
17 obligations, clause by clause.
17 obligations transcribed from the conditions of contract, each held with its clause, the window it sets and what missing it costs.
| Where it is written | The obligation | Window | If missed | Disease |
|---|---|---|---|---|
| cl 3.1.2-3.1.7 | Provide the contractor's bond within 2 monthsheld in the bank_guarantee register | 2 months | barred | Disputes |
| DZ cl 11.1, 11.2.1 | Notify defects within the 3 months defects notification periodheld in the punch_list register | 3 months | guidance | Disputes |
| cl 12.4.1 | Lodge the final payment claim within 1 months of the defects period endingheld in the progress_claim register | 1 month | barred | Disputes |
| cl 12.5 | Issue the final payment schedule within 20 working daysheld in the payment_schedule register | 20 working days | guidance | Disputes |
| cl 12.1.2, 12.2.1, 12.2.8secondary | Make a progress claim on the cadence the contract statesheld in the progress_claim register | 1 month | breach | Disputes |
| cl 12.3.3; DZ 12.3.4, 12.3.7 | Release retention within 10 working days of practical completion (or the defects period ending)held in the retention_position register | 10 working days | breach | Disputes |
| cl 10.3.5 | Decide an extension of time claim within 20 working daysheld in the contract_notice register | 20 working days | guidance | Missed claims |
| cl 10.3.2 | Give notice of an extension of time claim within 20 working daysheld in the contract_notice register | 20 working days | guidance | Missed claims |
| cl 5.10.1-5.10.4 | Submit the programme within 20 working daysheld in the programme register | 20 working days | barred | Missed claims |
| cl 9.5.3 | Give full details of an unforeseen physical conditionheld in the contract_notice register | none set | guidance | Lapsed compliance |
| cl 9.5.2, 9.5.4 | Notify an unforeseen physical condition as soon as practicableheld in the contract_notice register | none set | guidance | Lapsed compliance |
| cl 9.5.1 | Adverse weather is excluded from an extension of time claimheld in the contract_notice register | none set | guidance | Lapsed compliance |
| cl 9.4.3 | Record day works on the day they occurheld in the day_works_docket register | 1 day | guidance | Missed claims |
| cl 9.2.2secondary | Notify a variation claim within 1 months of the instructionheld in the contract_notice register | 1 month | guidance | Missed claims |
| cl 9.2.3secondary | Notify any other matter affecting time or cost within 1 monthsheld in the contract_notice register | 1 month | guidance | Missed claims |
| cl 9.3.2 | Propose the value of a variation within 1 months of the instructionheld in the contract_notice register | 1 month | guidance | Missed claims |
| cl 9.2.4secondary | Respond to a variation notice within 1 monthsheld in the contract_notice register | 1 month | guidance | Missed claims |
What this page is, and is not.
It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
Common questions
What does NZS 3910:2013 Conditions of Contract (2013/DZ public-comment redline) cl 3.1.2-3.1.7 require?
Provide the contractor's bond within 2 months. Missing it: barred. The window is 2 months. Demiton watches it against the bank_guarantee register.
What does NZS 3910:2013 Conditions of Contract (2013/DZ public-comment redline) DZ cl 11.1, 11.2.1 require?
Notify defects within the 3 months defects notification period. Missing it: guidance. The window is 3 months. Demiton watches it against the punch_list register.
What does NZS 3910:2013 Conditions of Contract (2013/DZ public-comment redline) cl 12.4.1 require?
Lodge the final payment claim within 1 months of the defects period ending. Missing it: barred. The window is 1 month. Demiton watches it against the progress_claim register.
What does NZS 3910:2013 Conditions of Contract (2013/DZ public-comment redline) cl 12.5 require?
Issue the final payment schedule within 20 working days. Missing it: guidance. The window is 20 working days. Demiton watches it against the payment_schedule register.
What does NZS 3910:2013 Conditions of Contract (2013/DZ public-comment redline) cl 12.1.2, 12.2.1, 12.2.8 require?
Make a progress claim on the cadence the contract states. Missing it: breach. The window is 1 month. Demiton watches it against the progress_claim register.
Does Demiton hold every obligation in NZS 3910:2013 Conditions of Contract (2013/DZ public-comment redline)?
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.