Skip to content
Demiton
Demiton
Contracts and standards / Western Australia

Main Roads WA Major Works Book 2, Conditions of Contract

conditions of contract, published by Main Roads Western Australia, Book 2. Western Australia.

Read the full text from Main Roads Western Australia. This page holds the obligations in it, not the document.

Demiton watches obligations in this document on live jobs, against the registers they already keep. Book a 30-minute call.

1 obligation, clause by clause.

1 obligation transcribed from the conditions of contract, each held with its clause, the window it sets and what missing it costs.

Where it is writtenThe obligationWindowIf missedDisease
SCC 10 (replaces cl 12)Notify a latent condition as soon as it is foundheld in the contract notice register28 daysthe costs cannot be recoveredMissed claims

Every notice in the Australian contract forms: Notices in construction contracts, Variation claims, Time bars, Final payment claim.

How the law works on an Australian job, state by state: Railways: rail safety and signalling, Australia: payment, WHS and contracts, Security of Payment Act.

Watch Main Roads WA Major Works Book 2, Conditions of Contract on your own jobs.

A clause in the table turns on a fact your jobs already record: a date, a notice, a record kept. Demiton reads that fact from the register and tells the person who signs off before the window shuts. Missing one costs what the If missed column says.

What this page is, and is not.

It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.

Clauses read from the obligation library, release v22, last checked against the source on .

Common questions

What does Main Roads WA Major Works Book 2, Conditions of Contract SCC 10 (replaces cl 12) require?

Notify a latent condition as soon as it is found. Missing it: the costs cannot be recovered. The window is 28 days. Demiton watches it against the contract notice register.

Does Demiton hold every obligation in Main Roads WA Major Works Book 2, Conditions of Contract?

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.