Main Roads WA Minor Works General Conditions of Contract
conditions of contract, published by Main Roads Western Australia, Oct 2025. Western Australia.
2 obligations, clause by clause.
2 obligations transcribed from the conditions of contract, each held with its clause, the window it sets and what missing it costs.
| Where it is written | The obligation | Window | If missed | Disease |
|---|---|---|---|---|
| GCC 9.6 | Claim an extension of time within 14 days of the delay startingheld in the contract_notice register | 14 days | barred | Missed claims |
| GCC 17.2, 17.4 | Update the programme within 1 monthsheld in the programme register | 1 month | breach | Missed claims |
What this page is, and is not.
It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
Common questions
What does Main Roads WA Minor Works General Conditions of Contract GCC 9.6 require?
Claim an extension of time within 14 days of the delay starting. Missing it: barred. The window is 14 days. Demiton watches it against the contract_notice register.
What does Main Roads WA Minor Works General Conditions of Contract GCC 17.2, 17.4 require?
Update the programme within 1 months. Missing it: breach. The window is 1 month. Demiton watches it against the programme register.
Does Demiton hold every obligation in Main Roads WA Minor Works General Conditions of Contract?
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.