Main Roads WA Minor Works General Conditions of Contract
conditions of contract, published by Main Roads Western Australia, Oct 2025. Western Australia.
Read the full text from Main Roads Western Australia. This page holds the obligations in it, not the document.
Demiton watches obligations in this document on live jobs, against the registers they already keep. Book a 30-minute call.
2 obligations, clause by clause.
2 obligations transcribed from the conditions of contract, each held with its clause, the window it sets and what missing it costs.
| Where it is written | The obligation | Window | If missed | Disease |
|---|---|---|---|---|
| GCC 9.6 | Claim an extension of time within 14 days of the delay startingheld in the contract notice register | 14 days | the claim is barred | Missed claims |
| GCC 17.2, 17.4 | Update the programme within 1 monthsheld in the programme register | 1 month | a breach of contract | Missed claims |
Extension of time, contract by contract: What is an extension of time?, EOT claims, Notice of delay, Late claims.
Every notice in the Australian contract forms: Notices in construction contracts, Variation claims, Time bars, Final payment claim.
Watch Main Roads WA Minor Works General Conditions of Contract on your own jobs.
A clause in the table turns on a fact your jobs already record: a date, a notice, a record kept. Demiton reads that fact from the register and tells the person who signs off before the window shuts. Missing one costs what the If missed column says.
What this page is, and is not.
It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
Clauses read from the obligation library, release v22, last checked against the source on .
Common questions
What does Main Roads WA Minor Works General Conditions of Contract GCC 9.6 require?
Claim an extension of time within 14 days of the delay starting. Missing it: the claim is barred. The window is 14 days. Demiton watches it against the contract notice register.
What does Main Roads WA Minor Works General Conditions of Contract GCC 17.2, 17.4 require?
Update the programme within 1 months. Missing it: a breach of contract. The window is 1 month. Demiton watches it against the programme register.
Does Demiton hold every obligation in Main Roads WA Minor Works General Conditions of Contract?
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
More in Western Australia
- Main Roads WA Major Works Book 2, Conditions of Contract1 obligation
- Main Roads WA Specification 201 Quality Management3 obligations
- Construction Industry Portable Paid Long Service Leave Act 1985 (WA)1 obligation
- Work Health and Safety (General) Regulations 2022 (WA), high risk work licences (rr 81 to 85)2 obligations
- Building and Construction Industry (Security of Payment) Act 2021 (WA)10 obligations
- Work Health and Safety Act 2020 (WA)3 obligations
- Work Health and Safety (General) Regulations 2022 (WA)8 obligations