GC21 (Edition 2) TfNSW General Conditions of Contract (C2-GC21 Ed 2 Rev 19)
conditions of contract, published by Transport for NSW, C2-GC21 Ed 2 Rev 19, December 2019. New South Wales.
2 obligations, clause by clause.
2 obligations transcribed from the conditions of contract, each held with its clause, the window it sets and what missing it costs.
| Where it is written | The obligation | Window | If missed | Disease |
|---|---|---|---|---|
| cl 28.3, 28.4, Schedule 17 | Prove to TfNSW that subcontractors and suppliers were paid within 5 business days of receiving each paymentheld in the subcontractor_payment register | 5 business days | a breach of contract | Disputes |
| cl 28.4, Schedule 17 | Pay the subcontractors and suppliers listed in each claim within 3 business days of receiving paymentheld in the subcontractor_payment register | 3 business days | a breach of contract | Disputes |
What this page is, and is not.
It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
Common questions
What does GC21 (Edition 2) TfNSW General Conditions of Contract (C2-GC21 Ed 2 Rev 19) cl 28.3, 28.4, Schedule 17 require?
Prove to TfNSW that subcontractors and suppliers were paid within 5 business days of receiving each payment. Missing it: a breach of contract. The window is 5 business days. Demiton watches it against the subcontractor_payment register.
What does GC21 (Edition 2) TfNSW General Conditions of Contract (C2-GC21 Ed 2 Rev 19) cl 28.4, Schedule 17 require?
Pay the subcontractors and suppliers listed in each claim within 3 business days of receiving payment. Missing it: a breach of contract. The window is 3 business days. Demiton watches it against the subcontractor_payment register.
Does Demiton hold every obligation in GC21 (Edition 2) TfNSW General Conditions of Contract (C2-GC21 Ed 2 Rev 19)?
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
More in New South Wales
- Aboriginal objects and places (National Parks and Wildlife Act 1974 (NSW))2 obligations
- Building and Construction Industry Long Service Payments Act 1986 (NSW)1 obligation
- Environment protection licence (Protection of the Environment Operations Act 1997 (NSW))2 obligations
- NSW GC21 Edition 2 General Conditions of Contract11 obligations · The form the whole NSW job is written on.
- Building and Construction Industry Security of Payment Act 1999 (NSW)9 obligations
- Security of Payment Regulation 2020 (NSW)1 obligation
- TfNSW G2-C2 General Requirements (TS 01566)3 obligations · The immaculate NSW bureaucracy, with a specification for everything.
- Transport for NSW QA Specification R44 Earthworks1 obligation · The NSW answer to the same question MRTS04 asks.