C41 Terms for Contracted Work (Minor Physical Works and Services), Transport for NSW
conditions of contract, published by Transport for NSW, RMS edition, document D11032802 (the public copy is ICAC exhibit E23-1349-AS-25-0001, 67 pages). New South Wales.
12 obligations, clause by clause.
12 obligations transcribed from the conditions of contract, each held with its clause, the window it sets and what missing it costs.
| Where it is written | The obligation | Window | If missed | Disease |
|---|---|---|---|---|
| cl 5.3 | Notify RMS in writing, promptly, of anything that may delay the progress of the Contracted Work, with details of the possible delay and its causeheld in the contract notice register | none set | a breach of contract | Missed claims |
| cl 5.4.2 | Give RMS written notice of a delay, with its details, causes and the extra time claimed, within 28 days of the start of the delayheld in the contract notice register | 28 days | the claim is barred | Missed claims |
| cl 9.2 | Write to the RMS Representative, before complying where possible and within 7 days of the direction, setting out why a direction that is not stated to be a variation direction is oneheld in the contract notice register | 7 days | the claim is barred | Missed claims |
| cl 5.2 | Perform the Contracted Work to the program submitted to RMS and notify RMS of every change to itheld in the programme register | none set | a breach of contract | Missed claims |
| cl 23.1.1, 23.1.2 | Submit each month's Payment Claim on the Payment Claim Day the Contract Schedule names, lodged electronically at the Contract Schedule addressheld in the progress claim register | 1 month | a breach of contract | Disputes |
| cl 4.6.3 | Submit with every Payment Claim a summary of product quality records showing each lot or component of the Contracted Work conforms with the Contractheld in the inspection test result register | 1 month | a breach of contract | Disputes |
| cl 4.6.4 | Retain quality records for at least 5 years after the end of the last warranty period, and give RMS access to them or deliver them on requestheld in the inspection test result register | 60 months | a breach of contract | Lapsed compliance |
| cl 20, 3.1 | Lodge the security the Contract Schedule requires, in cash or an unconditional undertaking in the Schedule 1 form, within 14 days of the date of RMS's letter accepting the tenderheld in the bank guarantee register | 14 days | a breach of contract | Lapsed compliance |
| cl 27 | After the last warranty period ends, request the release of the security; RMS releases it within 14 days of the request if satisfiedheld in the contract notice register | none set | no penalty stated | Missed claims |
| cl 3.2 | Satisfy the cl 3.1 conditions and start the Contracted Work within 14 days of the date of the Letter of Award, unless otherwise advisedheld in the site diary register | 14 days | a breach of contract | Lapsed compliance |
| cl 3.1.2, 19.1.3 | Before starting, give RMS certificates of currency for the insurances you must hold, and the details the RMS Insurer needs for Principal Arranged Insuranceheld in the insurance certificate register | none set | a breach of contract | Lapsed compliance |
| cl 29 | Respond to a show cause notice within 14 days, showing cause to RMS's satisfaction why the Contract should not be terminatedheld in the contract notice register | 14 days | a breach of contract | Disputes |
Extension of time, contract by contract: What is an extension of time?, EOT claims, Notice of delay, Late claims.
What this page is, and is not.
It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
Common questions
What does C41 Terms for Contracted Work (Minor Physical Works and Services), Transport for NSW cl 5.3 require?
Notify RMS in writing, promptly, of anything that may delay the progress of the Contracted Work, with details of the possible delay and its cause. Missing it: a breach of contract. The clause sets no day count. Demiton watches it against the contract notice register.
What does C41 Terms for Contracted Work (Minor Physical Works and Services), Transport for NSW cl 5.4.2 require?
Give RMS written notice of a delay, with its details, causes and the extra time claimed, within 28 days of the start of the delay. Missing it: the claim is barred. The window is 28 days. Demiton watches it against the contract notice register.
What does C41 Terms for Contracted Work (Minor Physical Works and Services), Transport for NSW cl 9.2 require?
Write to the RMS Representative, before complying where possible and within 7 days of the direction, setting out why a direction that is not stated to be a variation direction is one. Missing it: the claim is barred. The window is 7 days. Demiton watches it against the contract notice register.
What does C41 Terms for Contracted Work (Minor Physical Works and Services), Transport for NSW cl 5.2 require?
Perform the Contracted Work to the program submitted to RMS and notify RMS of every change to it. Missing it: a breach of contract. The clause sets no day count. Demiton watches it against the programme register.
What does C41 Terms for Contracted Work (Minor Physical Works and Services), Transport for NSW cl 23.1.1, 23.1.2 require?
Submit each month's Payment Claim on the Payment Claim Day the Contract Schedule names, lodged electronically at the Contract Schedule address. Missing it: a breach of contract. The window is 1 month. Demiton watches it against the progress claim register.
Does Demiton hold every obligation in C41 Terms for Contracted Work (Minor Physical Works and Services), Transport for NSW?
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.
More in New South Wales
- Aboriginal objects and places (National Parks and Wildlife Act 1974 (NSW))2 obligations
- Building and Construction Industry Long Service Payments Act 1986 (NSW)1 obligation
- Environment protection licence (Protection of the Environment Operations Act 1997 (NSW))2 obligations
- NSW GC21 Edition 2 General Conditions of Contract11 obligations · The form the whole NSW job is written on.
- Work Health and Safety Regulation 2025 (NSW), Part 4.5 Division 1 (Licensing of high risk work)2 obligations
- Building and Construction Industry Security of Payment Act 1999 (NSW)9 obligations
- Security of Payment Regulation 2020 (NSW)1 obligation
- GC21 (Edition 2) TfNSW General Conditions of Contract (C2-GC21 Ed 2 Rev 19)2 obligations