Native vegetation clearing (Local Land Services Act 2013 (NSW))

permit, published by Local Land Services NSW, Current version as archived 20 July 2025 in the NSW legislation XML export; read 2026-09-30. New South Wales.

Read the full text from Local Land Services NSW. This page holds the obligations in it, not the document.

Demiton watches obligations in this document on live jobs, against the registers they already keep. Book a 30-minute call.

The numbers Native vegetation clearing (Local Land Services Act 2013 (NSW)) sets.

Read from Current version as archived 20 July 2025 in the NSW legislation XML export; read 2026-09-30. The document itself is free from Local Land Services NSW, and your contract's annexures are what bind.

The five ways clearing in a regulated rural area is lawful

s 60N; Divisions 4 to 6; s 60O; Part 5B

RouteWhere it is writtenWho, and what it needs
An allowable activityDivision 4 and Schedule 5AThe landholder, or someone on their behalf. No approval under Part 5A; the activity must be on the Schedule and within its distance.
A land management (native vegetation) codeDivision 5, s 60SThe landholder, in accordance with the code. Not on land the regulations or the code exclude, and not a forestry operation.
An approval of the Native Vegetation PanelDivision 6, s 60ZFAvailable only on category 2-regulated land, for the purpose the application specifies.
Another legislative authoritys 60OClearing authorised by the provisions s 60O lists.
A private native forestry planPart 5BA forestry operation carried out under an approved plan.

Section 60N makes clearing native vegetation in a regulated rural area an offence unless the landholder establishes one of these. A regulated rural area is land that is category 2-regulated land on the native vegetation regulatory map (Sch 5A cl 1). None of the five excuses an approval another Act requires, and Schedule 5A says so of itself (s 60Q(2)).

Allowable activities, Schedule 5A Part 2: clearing that needs no approval

Sch 5A cll 13 to 27A

ClauseAllowable activityThe limit the Schedule puts on it
cl 13Removing or reducing an imminent risk of serious personal injury or damage to propertyOnly clearing reasonably necessary for that purpose.
cl 14Timber for the construction, operation or maintenance of rural infrastructure on the same landholdingNo land degradation; not threatened species or their habitat the landholder knows of.
cl 15FirewoodOnly where it cannot come from other authorised clearing; the same species limits.
cl 16Exempt farm forestry within the Plantations and Reafforestation Act 1999Not on land under a private native forestry plan.
cl 17Native vegetation that has been plantedNot if planted with public funds for a purpose other than forestry.
cl 18A traditional Aboriginal cultural activityNot a commercial cultural activity.
cl 19Environmental protection works: re-vegetation, bush regeneration, wetland, erosion and dune worksNot coastal protection works within the Coastal Protection Act 1979.
cl 20Infrastructure built, operated or maintained by a public authority or local councilIn the exercise of its land management activities; not threatened species or their habitat.
cl 21Gravel pitsBy or for a local council only; one area of at most 2 hectares, or 5 in the Western Zone; with a restoration program.
cl 22Telecommunications infrastructureBy the landholder or the infrastructure's owner.
cl 23Privately owned power lines on private landOnly clearing reasonably necessary to build, operate or maintain them.
cl 24Maintaining public electricity transmission utilitiesOnly at the direction of the body responsible; no new access roads or tracks, no removal of low groundcover, and within the voltage distances below.
cl 25Sustainable grazingGrazing and grassland management not likely to cause substantial long-term decline in native vegetation.
cl 25AMulga cut for stock fodder on the same landholdingAt most 50% of the holding's mulga in any 10 years; not on a small holding, in the Coastal Zone, on category 2-vulnerable land or within 20 metres of a watercourse.
cl 26An airstripThe minimum clearing civil aviation standards require.
cl 27A firebreak in the Western ZoneAt most 100 metres, where the vegetation is predominantly mallee.
cl 27AMaintaining public water supply and gas supply infrastructureBy the landholder or the infrastructure's owner.

Every allowable activity is clearing to the minimum extent necessary for its purpose (cl 7), and only by or on behalf of the landholder unless the clause says otherwise (cl 2). Part 4 of the Schedule adds limits on category 2-vulnerable and category 2-sensitive regulated land. Clearing on land under a Biodiversity Conservation Act 2016 Part 11 order is never authorised (cl 11).

How far you may clear for rural infrastructure: fences, roads, tracks, pipelines

Sch 5A Part 3, cll 29 to 31

Zone or holdingMaximum clearing distanceWhat counts as rural infrastructure there
Western Zone (the Western Division)40 metresFences, roads, tracks, irrigation channels and pipelines, water pipelines, soil conservation earthworks, cut lines for stock, bore drains, drains to water storages, telephone and power lines, areas for moving large machinery; sheds, stock handling facilities, dams, ground tanks, windmills, bores, pumps, tanks and water points (cl 29(2)).
Central Zone30 metresThe same list as the Western Zone (cl 29(2)).
Coastal Zone15 metresPermanent boundary and internal fences, roads, tracks and pipelines; shearing and machinery sheds, tanks, dams, stockyards, bores, pumps, water points and windmills (cl 29(3)).
A small holding in any Zone, or a temporary fence12 metresPermanent fences, roads, tracks and pipelines; windmills, bores, stockyards, buildings other than habitable ones, dams, pumps, tanks and water points (cl 29(4)). A small holding is under 10 hectares, or under 40 in the Western Zone (cl 4).

Rural infrastructure is infrastructure for an activity that may be carried out without development consent or State significant infrastructure approval under the Environmental Planning and Assessment Act 1979 (cl 29(1)(b)): on a consented job, the consent's conditions govern the clearing, not this Schedule. A distance is the total width for linear infrastructure and the distance from the perimeter for fixed-point infrastructure (cl 5); distances for neighbouring items are not added together (cl 6); Local Land Services may certify a larger distance for a legitimate purpose with only minor environmental impact (cl 10).

Clearing distances under electricity transmission lines

Sch 5A cl 24(3)(c)

Nominal operating voltageMaximum clearing distance
Not more than 11 kV20 metres
Above 11 kV, up to 33 kV25 metres
Above 33 kV, up to 66 kV30 metres
Above 66 kV, up to 132 kV45 metres
Above 132 kV, up to 330 kV60 metres
Above 330 kV70 metres

These apply to maintenance by, or at the written direction of, the body responsible for the utility (cl 24(2)). Constructing a new access road or track is not maintenance (cl 24(3)(a)).

What unauthorised clearing costs

s 60N

The offenceA corporationAn individual
Intentional, and caused or was likely to cause significant harmUp to $5 millionUp to $1 million
OtherwiseUp to $2 millionUp to $500,000

The maximums the obligation row records from s 60N. Outside the rural areas Part 5A covers, the Act's own note says clearing in a non-rural area is governed by the State Environmental Planning Policy (Vegetation in Non-Rural Areas) 2017 and the planning legislation, with a similar maximum penalty.

1 obligation, clause by clause.

1 obligation transcribed from the permit, each held with its clause, the window it sets and what missing it costs.

Where it is writtenThe obligationWindowIf missedDisease
ss 60N, 60ZFDo not clear native vegetation on the site without the development approval, or the notification, that the state's vegetation rules requireheld in the compliance evidence registernone setthe claim is barredLapsed compliance

How the law works on an Australian job, state by state: Railways: rail safety and signalling, Australia: payment, WHS and contracts, Security of Payment Act.

Watch Native vegetation clearing (Local Land Services Act 2013 (NSW)) on your own jobs.

A clause in the table turns on a fact your jobs already record: a date, a notice, a record kept. Demiton reads that fact from the register and tells the person who signs off before the window shuts. Missing one costs what the If missed column says.

What this page is, and is not.

It is the clause text this library holds for this document, with the window and the consequence. It is not legal advice, and it is not a substitute for reading the document you signed.

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.

Clauses read from the obligation library, release v22, last checked against the source on .

Common questions

What does Native vegetation clearing (Local Land Services Act 2013 (NSW)) ss 60N, 60ZF require?

Do not clear native vegetation on the site without the development approval, or the notification, that the state's vegetation rules require. Missing it: the claim is barred. The clause sets no day count. Demiton watches it against the compliance evidence register.

What are allowable activities under the Local Land Services Act?

The clearing of native vegetation that Schedule 5A authorises in a regulated rural area without any approval under Part 5A (s 60Q). Part 2 of the Schedule lists the general activities, from removing an imminent risk to public works and private power lines; Part 3 covers rural infrastructure such as fences, roads, tracks and pipelines, up to a distance set by zone. The clearing is only to the minimum extent necessary (cl 7), only by or on behalf of the landholder unless a clause says otherwise (cl 2), and the Schedule authorises nothing that another Act requires an approval for (s 60Q(2)).

Do I need approval to clear native vegetation in NSW?

In a regulated rural area, clearing native vegetation is an offence under s 60N unless one of five defences applies: it is an allowable activity under Schedule 5A, it follows a land management (native vegetation) code, it has a Native Vegetation Panel approval under s 60ZF, it is authorised under s 60O, or it is a forestry operation under a private native forestry plan. Outside the rural areas Part 5A covers, the planning system and the State Environmental Planning Policy (Vegetation in Non-Rural Areas) 2017 govern clearing instead.

How far can you clear for a fence, road or track in NSW?

For rural infrastructure, up to 40 metres in the Western Zone, 30 metres in the Central Zone, 15 metres in the Coastal Zone, and 12 metres on a small holding or for a temporary fence in any zone (Sch 5A cl 31). The distance is the total width of clearing for a road, track, fence or pipeline, and the distance from the perimeter for a shed, dam or tank (cl 5). Two items side by side do not add their distances together (cl 6).

Does Schedule 5A cover a construction site that has a development consent?

No. Rural infrastructure is infrastructure for an activity that may be carried out without development consent or State significant infrastructure approval under the Environmental Planning and Assessment Act 1979 (Sch 5A cl 29(1)(b)), and the Schedule does not authorise clearing that another Act requires an approval for (s 60Q(2)). On a consented job the clearing the consent and its conditions allow is the clearing you may do, and the vegetation management plan under that consent is what the site is audited against.

What is the penalty for clearing native vegetation without approval in NSW?

Under s 60N, up to $5 million for a corporation and $1 million for an individual where the clearing was intentional and caused, or was likely to cause, significant harm, and up to $2 million or $500,000 otherwise.

Who may carry out allowable activity clearing?

The landholder, or someone acting on the landholder's behalf (Sch 5A cl 2). Two clauses extend that to the owner of the infrastructure, telecommunications (cl 22) and water and gas supply (cl 27A), but the Schedule gives no right to enter the land to do it (cl 2(2)). A contractor clearing for a landholder is clearing on the landholder's behalf, and the landholder's defence under s 60N is the one that has to hold.

Does Demiton hold every obligation in Native vegetation clearing (Local Land Services Act 2013 (NSW))?

No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.