How do you claim an extension of time?
An EOT claim is the written claim for more time that follows a delay. Each form starts its own clock. AS 4000, AS 2124 and GC21 count 28 days from the delay starting. AS 4902 counts 28 days from when the cause should reasonably have been known. The TMR TIC allows 20 business days.
When the clock starts
The library holds two start events. Most forms count from the delay starting: AS 4000, AS 2124, GC21, the TMR TIC and Main Roads WA Minor Works. AS 4902 counts from when the delay's cause should reasonably have been known, which can be later.
How long it runs
| Contract | Extension of time claim |
|---|---|
| AS 2124-1992 | 28 daysClaim an extension of time within 28 days of the delay startingcl 35.5If missed: the claim is barred |
| AS 4000-1997 | 28 daysClaim an extension of time within 28 days of the delay startingcl 34.2, 34.3, 34.5If missed: the claim is barred |
| AS 4902-2000 | 28 daysClaim an extension of time within 28 days of when the delay's cause should reasonably have been knowncl 34.2, 34.3, 34.5If missed: the claim is barred |
| GC21 Ed 2 (ACT) | not held in the library |
| GC21 Ed 2 (NSW) | 28 daysClaim an extension of time within 28 days of the delay startingcl 50.3If missed: reduced for each day late |
| TfNSW C2-GC21 | not held in the library |
| TfNSW C41 | 28 daysGive RMS written notice of a delay, with its details, causes and the extra time claimed, within 28 days of the start of the delaycl 5.4.2If missed: the claim is barred |
| TMR TIC | 20 business daysClaim an extension of time within 20 business days of the delay startingcl 35.5(c), (h), (l)If missed: the claim is barred |
| Main Roads WA Major Works | not held in the library |
| Main Roads WA Minor Works | 14 daysClaim an extension of time within 14 days of the delay startingGCC 9.6If missed: the claim is barred |
New Zealand's forms work by a notice of the claim instead, 20 working days under NZS 3910:2013 (cl 10.3.2): see notice of delay.
Days, business days, working days
The forms count differently. AS 4902: days are calendar days (cl 1). The TMR TIC counts business days (20 business days for the claim). NZS 3910 counts working days (20 working days for the notice). Demiton does not print a dated deadline for these: the library does not yet hold each form's rule for which days count.
When the delay keeps going
- GC21 cl 50.3Updated every subsequent 28 days while the delay continues.
- NZS 3910:2023 (draft)A continuing delay may be notified more than once.
The library holds no rule on a continuing delay for the other forms.
Weather
- NZS 3910:2013 cl 9.5.1Weather is not an unforeseen physical condition, but cl 10.3.1 lists weather sufficiently inclement to interfere with the progress of the works as a ground for an extension of time.
- Main Roads WA Minor WorksWeather judged against meteorological averages.
- TfNSW G2-C2 cl 43Record wet weather days against the programme. Named in each EOT claim, no separate numeric window stated. Delay costs recoverable only above a per-project threshold.
The record the claim stands on
A claim is measured against the programme. The Contract Program is what every later extension-of-time claim is measured against (cl 50.1). These are the programme duties the library holds; each is a breach of contract when missed, except where the table says otherwise.
| Contract | Programme |
|---|---|
| GC21 Ed 2 (NSW) | 14 daysSubmit the Contract Program within 14 days after the Date of Contractcl 22.1If missed: a breach of contract1 monthUpdate the programme within 1 monthscl 22.3If missed: a breach of contract |
| TfNSW G2-C2 | 1 monthUpdate the programme within 1 monthscl 39.2If missed: a breach of contract |
| TMR TIC | 1 monthUpdate the programme within 1 monthscl 33.4.9If missed: a breach of contract |
| Main Roads WA Minor Works | 1 monthUpdate the programme within 1 monthsGCC 17.2, 17.4If missed: a breach of contract |
| New Zealand | |
| NZS 3910:2013 | 20 working daysSubmit the programme within 20 working dayscl 5.10.1-5.10.4If missed: the claim is barred |
- NZS 3910:201310 WD after acceptance of tender for the initial programme; the 20 working days is for the full programme.
- TMR TIC cl 33.2.1, 33.2.2Submit the daily report within 1 business days. Due by 11.00am the following Business Day. Only required where Item 34A of the contract particulars applies.
- Site photographsNo Australian primary source names a photo cadence. Demiton's default is dated, located photographs every working day, from the SCL Delay and Disruption Protocol (App B 2.2-2.3). The one-per-working-day cadence and the dated-and-located content requirement are the Demiton default, not a source's. It is guidance: a day without photographs is never counted as missed.
Templates and examples
Not here. The library holds each form's window, clause and the cost of missing it, not the wording a claim must carry, and wording is drafting. Use the clause on the form's own page and your contract's special conditions. What the library can give you is the checklist above: the window, the start event, the clause and what a late claim costs, for the form you are on. What a late claim costs, form by form, is on late claims.
What this page is, and is not
It is the clause, window and consequence this library holds for each published contract form. It is not legal advice, and it is not your contract: a principal's special conditions can change any window and any consequence here, so read the contract you signed.
No library of law is complete, and Demiton never says this one is. An obligation the library does not hold, and you did not add, is not protected. You can add your own to any job.